Attendees

Regrets

Discussion Items

ItemWhoNotes
Notes
last time
Project Updates
  • filter stuck in loader (arms did not release), also safety issue at SLAC concerning filter (may require procedure update for suspended load).
  • Visa received, Flights booked for June 3
  • Transition to ops meetings (DM 8:30 PT Tomorrow)
  • Risk meeting Thursday .. should be in context of revised schedule.
  • Review .. bit of debacle .. trying to sort it out
  • Scope options -
    • only EPO tablets seem to be on table (after replan)
    • m3 optical testing descope becomes not available (Hardware purchased)
  • Andrew Heyer left - so now lack of resources in TSSW.
  • Mass simulator shipping stopped
    • batteries in new accelerometers too powerful (need to use old ones)
  • 3 month lead on cable for camera ..
    • Cristian controls computer room to pier,
    • top of pier through TMA apparently Jacques .. IT helping but someone on telescope needs to physically help climbing up on TMA and measuring.
    • Kevin working on this last 3 weeks ..
    • service loop allows some play but
    • Greg worried that cable from pier to top
      • unterminated fibre purchased
      • has not seen drawing on the termination nor part numbers
      • Kevin says a document has been provided with this .
        • plus Greg apparently has specified the terminators.
  • Kevin to DMLT later .. planning for next year
PCW

Save the date, August 9-13, for the 2021 Rubin Project and Community Workshop (PCW), which will be virtual again this year.

  • DM all hands?
    • Yes, should collect ideas for an all-hands.
DEI


See  #inclusion and https://www.lsst.org/about/dei

Community link: https://community.lsst.org/c/eji/45

Review

Confluence Replan review

Our docs https://docs.google.com/spreadsheets/d/1cffxo8wCtQrw0KQqAjyNZ00HWtQI5pIPuF25CVacO2A/edit#gid=0

Review your documents

Slide decks https://drive.google.com/drive/folders/1pB6OxZFy7rVoTuCr5gChGtC2P3Aa5ZRa

  • milestone cliff (not the one in presentation)
Level 2 Milestones


see also LSST Verification & Validation Documentation

Test Plans due in the next 45 days

Key Summary T Created Updated Due Assignee Reporter P Status Resolution
Loading...
Refresh

Milestones due in the next 45 days

Key Summary T Created Updated Due Assignee Reporter P Status Resolution
Loading...
Refresh

Risk Review




Risk items needing review

Key Summary T Created Updated Due Assignee Status days since review
Loading...
Refresh

Overdue risks (obligation date passed)

T Key Summary Assignee Reporter P Status Resolution Created Updated Due
Loading...
Refresh

Risk mitigations due at the end of this month

Key Summary T Created Updated Due Assignee Reporter P Status Resolution
Loading...
Refresh

Overdue risk mitigations

 

T Key Summary Assignee Reporter P Status Resolution Created Updated Due
Loading...
Refresh

DMLT Travel & Availability this week



Any Other Business



TCAM Stamdup

Kevin Long will tell us whats needed for "replan" activities :  "Convert all planning package activities forecasted to start within three months of the schedule status date (minimum, six months preferred) to the work package level of detail, in accordance with the EVMS System Description.* (Guideline 10)"

Would it be possible to do a big replan for the next year to give us a cushion for whenever this next surveillance is going to be?

Discussion:

  • planning package details needed 3 months out ..
  • not well enforced in DM but last survelance more planning was looked for.
  • Kevin sees a framework which is common
    • can we plan out to end of project?
    • do not need every detail
    • do 3 month epics - does not need to be all the budget.
    • can do bigger packages and LCR changes closer to the - tie to Jira epics
    • What about planning packages on books ?
      • detail what you have and Kevin will put the planning packages at the end..
      • so some epics .. to the end ..  keep the rest int the planning package at then end
    • How much should we do ?
      • e..g Frossie always has similar epics (Kevin could probably do 50%)
      • and we still provide updates each 3 months.
    • Kevin explains the EPICs provided each 3 months reduce the planning packages.
    • When ?
      • Survelence will be in August .. we did DM plan to June  so first week of June . 
      • Usual cycle plan format .. even as 3 worksheets ..
  • Frossie Economou  provide epics for 50-60% of team effort out to May 2022 to K. Long  
  • Yusra AlSayyad provide epics for 50-60% of team effort out to May 2022 to K. Long
  • Unknown User (mbutler)  provide epics for 50-60% of team effort out to May 2022 to K. Long
  • Fritz Mueller provide epics for 50-60% of team effort out to May 2022 to K. Long
  • Ian Sullivan provide epics for 50-60% of team effort out to May 2022 to K. Long
Action review



RFCs

Overdue

Key Summary Reporter Assignee Created planned end
Loading...
Refresh

Due this week

Key Summary Reporter Assignee Created planned end
Loading...
Refresh

Action Items

Confluence Quick Tasks

DescriptionDue dateAssigneeTask appears on
  • Frossie Economou Will recommend additional Level 3 milestones for implementation beyond just the DAX-9 Butler provenance milestone.   
15 Mar 2022Frossie EconomouDM Leadership Team Virtual Face-to-Face Meeting, 2022-02-15 to 17
  • Kian-Tat Lim Convene a meeting with Colin, Tim, Robert, Yusra to resolve graph generation with per-dataset quantities (likely based on Consolidated DB work).  
18 Mar 2022Kian-Tat LimDM Leadership Team Virtual Face-to-Face Meeting, 2022-02-15 to 17
  • Frossie Economou Write an initial draft in the Dev Guide for what "best effort" support means  
17 Nov 2023Frossie EconomouDM Leadership Team Virtual Face-to-Face Meeting - 2023-Oct-24
  • Convene a group to redo the T-12 month DRP diagram and define scope expectations Yusra AlSayyad 
30 Nov 2023Yusra AlSayyadDM Leadership Team Virtual Face-to-Face Meeting - 2023-Oct-24
11 Dec 2023Gregory Dubois-FelsmannDM Leadership Team Virtual Face-to-Face Meeting - 2023-Oct-24
02 May 2024Frossie EconomouDMLT Meeting - 2024-04-22
22 May 2024 DMLT Meeting - 2024-04-22
22 May 2024Fabio HernandezDMLT Meeting - 2024-04-22
  • Richard Dubois USDF part in data facilities for PSTN-017 and distrib processing ? 
22 May 2024Richard DuboisDMLT Meeting - 2024-04-22
  • Tim Jenness - section on middleware for PSTN-017  
22 May 2024Tim JennessDMLT Meeting - 2024-04-22
  • Cristián Silva - section on summit/data acquisition  for PSTN-017  
22 May 2024Cristián SilvaDMLT Meeting - 2024-04-22

DMLT-relevant Jira Tickets

Key Summary Reporter Assignee Created Due
Loading...
Refresh