(back to the list of all DMLT meeting minutes)

Location

Zoom link in bookmark on #dm-camelot  on slack

Time

10:15am PT

Attendees




Regrets

Discussion Items

ItemWhoNotes
Notes
last time
Project UpdatesFrossie Economou 
  • AMCR call this week, Wil only probably
  • Computer purchases discussion - AURA routing our joint ops/const reqs to NOIRLab's IT for approval
  • Summit contact for emergencies discussion - in progress
Report
done thank you
variances
Ian, Yusra, Cristian,  also Crisitan status on FIU Kevin asked for.
AMCR
Wednesday 12:00-15:00 EDT  I added two DM slides for victor https://docs.google.com/presentation/d/1hg49EillVGQRAIQJh5JOuUaGoiT-S4mWEx0_Te6hQyI/edit#slide=id.g1f4b32270b0_0_12
Review

2024 - JOR  April 16-18


Review of Project Milestones


https://www.lsst.org/about/project-status

DMTN-158 now with feb data

Level 2 Milestones


See also LSST Verification & Validation Documentation and docsteady.lsst.io.

Test Plans due in the next 45 days

Key Summary T Created Updated Due Assignee Reporter P Status Resolution
Loading...
Refresh

Milestones due in the next 45 days

Key Summary T Created Updated Due Assignee Reporter P Status Resolution
Loading...
Refresh

Risk Review




Risk items needing review

Key Summary T Created Updated Due Assignee Status days since review
Loading...
Refresh

Overdue risks (obligation date passed)

T Key Summary Assignee Reporter P Status Resolution Created Updated Due
Loading...
Refresh

Risk mitigations due at the end of this month

Key Summary T Created Updated Due Assignee Reporter P Status Resolution
Loading...
Refresh

Overdue risk mitigations

 

T Key Summary Assignee Reporter P Status Resolution Created Updated Due
Loading...
Refresh

DMLT Travel & Availability this week



Any Other Business



Action review



RFCs

Overdue

Key Summary Reporter Assignee Created planned end
Loading...
Refresh

Due this week

Key Summary Reporter Assignee Created planned end
Loading...
Refresh

Action Items

Confluence Quick Tasks

DescriptionDue dateAssigneeTask appears on
  • Frossie Economou Will recommend additional Level 3 milestones for implementation beyond just the DAX-9 Butler provenance milestone.   
15 Mar 2022Frossie EconomouDM Leadership Team Virtual Face-to-Face Meeting, 2022-02-15 to 17
  • Kian-Tat Lim Convene a meeting with Colin, Tim, Robert, Yusra to resolve graph generation with per-dataset quantities (likely based on Consolidated DB work).  
18 Mar 2022Kian-Tat LimDM Leadership Team Virtual Face-to-Face Meeting, 2022-02-15 to 17
  • Frossie Economou Write an initial draft in the Dev Guide for what "best effort" support means  
17 Nov 2023Frossie EconomouDM Leadership Team Virtual Face-to-Face Meeting - 2023-Oct-24
  • Convene a group to redo the T-12 month DRP diagram and define scope expectations Yusra AlSayyad 
30 Nov 2023Yusra AlSayyadDM Leadership Team Virtual Face-to-Face Meeting - 2023-Oct-24
11 Dec 2023Gregory Dubois-FelsmannDM Leadership Team Virtual Face-to-Face Meeting - 2023-Oct-24
02 May 2024Frossie EconomouDMLT Meeting - 2024-04-22
22 May 2024 DMLT Meeting - 2024-04-22
  • Richard Dubois USDF part in data facilities for PSTN-017 and distrib processing ? 
22 May 2024Richard DuboisDMLT Meeting - 2024-04-22
22 May 2024Fabio HernandezDMLT Meeting - 2024-04-22
  • Tim Jenness - section on middleware for PSTN-017  
22 May 2024Tim JennessDMLT Meeting - 2024-04-22
  • Cristián Silva - section on summit/data acquisition  for PSTN-017  
22 May 2024Cristián SilvaDMLT Meeting - 2024-04-22

DMLT-relevant Jira Tickets

Key Summary Reporter Assignee Created Due
Loading...
Refresh