Available Manpower

NameSPsNote
Bosch

43

Scientist, leader, 0.5 time
Gee780.5 time
Lupton366 SPs per month
MacArthur126Scientist
Price63

Scientist, 0.5 time

Swinbank87Scientist, leader
Total433 

 

LDM-240 Goals for FY15

WBS 02C.04.01 (App framework for catalogs)

  • Development in support of use cases utilizing catalog data

 

WBS 02C.04.03 (PSF Estimation)

  • Improved PSF estimation and interpolation (Kriging interpolation)
  • Integration of wavefront estimation code into the DM stack

WBS 02C.04.06 (Object Characterization)

  • Greedy optimizer for multi-epoch data

  • Multi-epoch extended source fits
  • Micro-optimized MultiFit model evaluation code

Summary of W15 Epics

NB "done" totals reflect only stories marked as done; not awarding "partial credit" for in review or similar.

Totals are based on mental arithmetic (so are only approximately correct), calculated on 22 Jan.

WBS 02C.04.01 (App framework for catalogs)

WBS definition

To what extent is all the work on the measurement framework best categorized as "app framework for catalogs"? Work on afw::table etc clearly is, but adjustments to measurement algorithms seem like they would better fit in a different WBS.

Measurement - Aperture Corrections DM-85 - Getting issue details... STATUS

Not meaningfully addressed in W15.

Estimated 31 SPs; planned 31 SPs; done 0 SPs.

This work is well defined & planned.

This is under a DRP WBS, but most of the work is (apparently?) to be done by UW/Krughoff/Owen.

Candidate to roll over to S15.

Measurement - Calibration and Ingest  DM-1074 - Getting issue details... STATUS

Aim to have this finished in W15.

Estimated 20 SPs; planning incomplete, currently at 11 SPs; done 1 SP.

afw::table - finish interface transition  DM-1099 - Getting issue details... STATUS

Aim to have this finished in W15.

Estimate 36 SPs; planned 36 SPs; done 8 SPs.

Measurement - Convert old algorithms  DM-1100 - Getting issue details... STATUS

Aim to have this finished in W15.

Estimated 31 SPs; planned 50 SPs; done 20 SPs.

Measurement - Finish framework overhaul  DM-1101 - Getting issue details... STATUS

Aim to have this finished in W15.

Estimated 51 SPs; planned 74 SPs; done 45 SPs.

afw - Footprint improvements  DM-1107 - Getting issue details... STATUS

Unlikely to be finished in W15.

Estimated 30 SPs; planned 53; done 15.

Measurement - Design MultiFit Plugin Framework  DM-1109 - Getting issue details... STATUS

Candidate to roll over to S15.

Estimated 20 SPs; unplanned; done 0.

NB, implementation of this plugin framework to be scheduled in S15 after design.

WBS 02C.04.03 (PSF Estimation)

No work planned in this cycle.

WBS 02C.04.06 (Object Characterization)

Work on ideas for the deblender  DM-1382 - Getting issue details... STATUS

This epic needs refocus and refactoring.

Not estimated; planned 140 SPs; done 0.

Suggestion: split into three epics ("Preparatory infrastructure"; "Investigate deblending in one band followed by using the resulting templates in all bands"; "Investigate deblending in one band followed by linear fits of models"). Roll all of them over to S15.

Other outstanding work

There are some  Getting issues...  in JIRA with no defined epic. They cannot therefore be scheduled for EVM. Most of these are relatively minor bug fixes or feature requests; those with SP estimates have no more than 4 SPs per issue. (That said, 35 issues at 2 SPs per issue is still 70 SPs, which is a major epic's worth of work).

We should consider if we can either add some of these to existing epics or combine them to create new ones.

HSC "Synergy"

HSC work which is ready for porting to LSST

Multi-band processing? Others?

HSC work which will be carried out in S15 with direct relevance to LSST

?

Outline S15 epics

WBS 02C.04.01 (App framework for catalogs)

EpicSP estimateLikely assignee(s)Note
DM-8531Bosch + UW?!Rolling over from W15
DM-110723Bosch, SwinbankRolling over from W15
DM-110920BoschRolling over from W15
Child-of-110950GeeImplement MultiFit plugin framework

What does Gee do while waiting for DM-1109?

WBS 02C.04.03 (PSF estimation)

No issues currently planned. We will need to complete some work here to meet our LDM-240 obligations.

WBS 02C.04.06 (Object Characterization)

EpicSP estimateLikely assignee(s)Note
Child-of-138260MacArthur, Price"Preparatory infrastructure for deblender"
Child-of-138240MacArthur"Investigate deblending in one band followed by using the resulting templates in all bands"
Child-of-138240MacArthur"Investigate deblending in one band followed by linear fits of models"
DM-110876BoschGalaxy Fitting - Shear Precision Experiments
DM-111060BoschGalaxy Fitting - Sampling Algorithm Plugin

Total SP allocations

Based on outline tasks above; simply dividing equally among likely assignees for now.

AssigneeSP
Bosch167
Gee50
Lupton0
MacArthur110
Price30
Swinbank12
UW/Krughoff/Owen16
  • No labels