Current plan is to execute OPS Rehearsal #2 the week of July 27th

  • pre-meeting July 27th (10am PST)
  • rehearsal activities July 28-30
  • Confluence page being used by the OPS rehearsal is linked HERE.


Robert Gruendl is leading this effort.

LDM-643 (Section 3) now has a first draft of a description for OPS rehearsal #2

Draft test plan for OR2 can be found at:  https://jira.lsstcorp.org/secure/Tests.jspa#/testPlan/LVV-P72


The pre-operations team feel using AuxTel for this rehearsal would provide maximum end-to-end realism.

(Though Covid-19 may prevent that)


Personnel needed to execute the rehearsal - Wil O'Mullane Chuck Claver Unknown User (mbutler)  with DM CAMS should identify staff for the rehearsal.

  • SIT-Com: Tiago, Patrick - if AUXTel with LATISS these two should be on site in Chile - and Brian (possibly Michael Reuter for EFD)
  • Data Production QA : Lauren , Yusra AlSayyad since it looks like we will be defining procedures as we go, others ..
  • Data Production Facility :  Michelle B, Robert G ,
  • TSSW: On call who Andy Clements


OPS rehearsal II discussion (2020 March 31; 15:00 Pacific; https://bluejeans.com/206063043)

Participants

Agenda

  • decide if we do it with simulations from the base or delay to summit reopening.
    • basically set a schedule
    • if we use LATISS agree ground rules with Patrick (not to interfere with engineering work)
    • ComCam?
  • give some clarity on personnel involved and what role they play
  • give some clarity on goals such as
    • which procedures we might develop
    • which requirements  could potentially verify (Jeff Carlin)

Notes

Goals:

  • Refer to LDM-643.
  • “Prepare for ComCam on the sky”.
    • How will observing proceed?
    • How will changes be folded in?
    • How will processing be incorporated into the daily operations of the system?
  • Inform e.g. our approach to change control: how do you change how the DAC is read out? How do you fall back to a previous system?
  • Exercise whatever systems we have available, or use shims to make the rehearsal possible.
  • However, the real aim is the interaction between the various teams (summit, Tucson, LDF); reality of hardware etc is not fundamental.
    • However, using hardware to make the rehearsal “hands-on” makes it more compelling.
    • Previous rehearsal was based on simulated data.
  • This is a commissioning rehearsal, rather than preparation for a steady state operations scenario.
  • Expect to plan a twist for mid-rehearsal; assume that everything runs smoothly on the first day.
    • Needs a “ringmaster” to make this happen.

Outstanding questions:

  • Which instrument should we use to drive the rehearsal? Simulations, or AuxTel/LATISS, or ComCam?
    • In the near term, AuxTel will be in stasis; ~months before it is back online.
    • Probability ComCam will be running in La Serena at some level, but it's not clear what level of connectivity it will have.
      • Wil reckons “quite a bit”; it's in the data center.
      • A moving target in terms of availability.
      • Could be used to generate biases, darks, flats.
    • Could play fake images through the NCSA test stand. This obviously doesn't exercise ComCam hardware.
      • Can inject “interesting” images, but it takes some effort.
    • Decision: target ComCam in the Recinto.
      • Backup plan: use test stand at NCSA if ComCam is not available. Specifically, the date takes priority over the hardware availability.
  • What compute hardware do we use?
    • The commissioning cluster should be available.
    • Also want to exercise batch compute as part of this exercise at NCSA.
  • When do we feel we need to run this rehearsal?
    • Do we need to rethink ops rehearsals given our current situation? E.g. introducing more rehearsals in future, as things start coming back online.
      • Note there is a pre-ops milestone which may fold in to this rehearsal.
      • That milestone implies we want this done by the end of June. 
    • Aiming for May gives enough time to get ComCam up and running, but likely the summit will still be closed so people will be available.
      • There is still some managerial work to be worked out to get ComCam going.
      • As above, date takes precedence, and we use the test stand if ComCam isn't available.
    • Some uncertainty about the availability of code to perform ingestion by May.
    • Note DMLT meeting, DES collaboration meeting in May.
    • Decision: Doodle poll key individuals for three days in May.
      • But can reconsider if ingestion is unavailable on that timescale.
  • How long should the rehearsal last?
    • Three days last time; allows time for handovers, debriefs, etc.
    • Decision: the duration will be at least three nights (four calendar days).
      • If the exercise is run during the day using ComCam in Recinto, then the equivalent of three nights is fine.
  • Who are the key personnel?
    • Chile: Kevin Reil, Brian Stalder (likely as observing scientist; alternatives are Sandrine Thomas, Chuck Claver, Kevin Reil, Tiago Ribeiro), Cristian Silva
    • Tucson: Michael Reuter, Patrick Ingraham (& Chuck as observer).
    • Execution staff / NCSA: Monika Adamow, JD Maloney, Robert Gruendl, Matt Kollross
    • SDQA: Lauren MacArthur, Jeff Carlin
      • Depends on exactly what pipelines get run, what high-level requirements can we test?
    • Pipelines support (on call): Merlin Fisher-Levine
    • Camera support (on call): Tony Johnson, Htut Khine Win, Steve
    • Director: Bob Blum
    • Several observers.


Next steps:



Plan Assuming ComCam available from Recinto/Base:

Prereq(s):

  • ComCam functioning (cold with illumination sources)
  • ComCam DAQ/Archiver produces appropriate headers
  • CPP pipeline ready to process (bias, dark, flat?)
  • Hexapod/Rotator simulators at a minimum (the more the better)

Rehearsal Outline/Script (repeat 3? times):

  • Observations from ComCam:
    • bias sequence
    • dark sequence
    • flat sequence?
  • Transfer and ingest to OODS (base) and DBB (NCSA)
  • CPP pipelines (triggered by hand?)
  • SDQA and inspection within LSP
  • Meet and discuss

Variance/Challenges:

  • initially, whatever might come up
  • Perform standard visit with ingest, display image post-ISR
    • ISR quality is somewhat irrelevant
    • Pretend bias is bad and new one is needed
      • Recreate master bias at NCSA excluding image 4
      • Get it to summit network, ingested and re-display the image with proper bias
      • Take a new image and make sure it uses the new bias
  • Simulate a normal commissioning characterization activity
    • Verify readout noise during slew is the same as when not in motion
      • Verify no pickup from motors etc
      • Check each elevation, azimuth and rotator axis independently
    • Analyze the data during the "day" at NCSA
  • A list of standard commissioning "challenges" forcing on-the-fly actions will be compiled increasing in difficulty
    • Will not be shared with participants prior to starting the exercise
  • Other daytime activities could include:
    • could attempt a DAQ upgrade w/ reversion (test change control/failover)
    • minor change in XML interface requiring re-deployment of a single component or two (not the entire system)

Potential Verification Elements:  (Note these might not be true verification of system requirement but more tests that elements can be verified)



OPS rehearsal II discussion (2020 May 20 )


Robert Gruendl 

Patrick Ingraham

Sandrine Thomas

Wil O'Mullane

Chuck Claver

Lauren MacArthur

Michael Reuter

Felipe Menanteau

Brian Stalder

Jeffrey Carlin

John Swinbank

Merlin Fisher-Levine

Robert Blum

Leanne Guy


Run June 2-4 inclusive.

Meeting noon each day . (See also LDM-643)

Take data in the morning and talk about it at noon. Discuss next day.

Comcam is available ! Some data transfers - but not triggered from outside (aka OCS) - test stand directory structure - rsync no acknowledgement.

Chuck asks how it gets in platform - cron job. Newer system should use less cron jobs.

Image format - they can be ingested but can not read them (in same nublado instance) .. since TSSW is on old version of stack so the SAL aware nublado container cannot read images. Regular LSP should work. Felipe says they are all good.

Weekly stack should be able to process the images. Headers are not same as CCS - need to check if there is any header info missing. Archiver generated files preferable but we may not get them. We can try camera generated files for now - no filter info in header, pretty much all other info is in the header.

Run calibration products generation and use those products on an image, not automatic, so perhaps generate them after each day?

Chuck suggests - Bias, Dark,Flats with illumination change - create master bias, dark, do ISR on flat images and produce master flat. Done manually for now but in ops its not necessarily automatic anyway. 

Kevin or Petr can theoretically go in and change a lamp or such.

Success  still looks like data arriving at NCSA and people looking at it.

  • Robert Gruendlwill provide a script and we will think about whether there is a blocker based on Archiver availability.


Proposed Outline/Script for OPS Rehearsal #2

Simulated
Time
Rehearsal
Time (PST)

Activity

Actor(s)Description
Day 0June 1, NoonPre-meetingALLA hopefully quick session to make sure we have all our ducks in a row.
#Afternoon
(DAY 1)
#Morning
June 2




9amAcquire afternoon calibration.ObsOpsSimple Calibration Sequence:  N? x bias, N? x flat, Dark sequence


Calibrations Products Pipeline USDF

11amExamine CalibrationsSciOps

Noon

Afternoon Stand-up Operations Meeting.

ALL


Close Out previous night's reportSciOps


Reprocessing (if needed)USDF


Select Configurations and Calibration SciOps
#Night



#Afternoon
(DAY 2)
#Morning
June 3




9amAcquire afternoon calibration.ObsOpsCalibration Sequence (change illumination source) and repeat Day 1


Calibrations Products Pipeline USDF

11amExamine CalibrationsSciOps

Noon

Afternoon Stand-up Operations Meeting.

ALL


Close Out previous night's reportSciOps


Reprocessing (if needed)USDF


Select Configurations and Calibration SciOps
#Night



#Afternoon
(DAY 3)
#Morning
June 4




9amAcquire afternoon calibration.ObsOpsCalibration Sequence:
 N x Bias,
 M x Flat (interrupt or change illumination during sequence)
 N x Flat (take good sequence)
Dark Sequence


Calibrations Products Pipeline USDF

11amExamine CalibrationsSciOps

Noon

Afternoon Stand-up Operations Meeting.

ALL


Close Out previous night's reportSciOps


Reprocessing (if needed)USDF


Select Configurations and Calibration SciOps
#Night



#Afternoon
(DAY 4)
#Morning
June 5





Network configuration changeKantorThe purpose being to test fail-over routing

10amAcquire afternoon calibration.ObsOpsOne set of BIAS(?)


Verify Data Arrival and ArchivingUSDF


No Need for General Meeting


next weekWrite Tech Note to Summarize/Discuss RehearsalAllAll really refers to 