(all times Central)
Planned work (in priority order)
- qserv-master migration
- pfSense updates
- Dell firmware updates
- routine patching and reboots
- final verification
Affected Hosts
- NPCF:
- all nodes (adm01, backup01, bastion01, monitor01, object*, qserv*, sui*, verify-worker*, test0*): 0800 - 1200
- qserv-master01: 0800 - 1600
- (NCSA 3003: ...)
Timeline for work during this maintenance event
Item # | Event | Planned Start | Duration | Comments | Who |
---|---|---|---|---|---|
1 | qserv-master migration | 0800 hrs | 8h | provision new hardware, move data from old server to new | Andrew Loftus |
2 | pfSense updates (NPCF) | 0800 hrs | 30m | firmware updates | Security |
3 | Dell firmware updates (NPCF) | 0830 hrs | 1h | Jacob Rundall | |
4 | routine patching and reboots (NPCF) | 0930 hrs | 1h | Jacob Rundall | |
5 | final verification (NPCF) | 1030 hrs | 1.5h | includes buffer time | Jacob Rundall |
Pre Outage
- Set reservation in scheduler
TBD
Outage
TBD
Rollback
TBD
Post Outage
- Igor would like to test before unracking the old server.