Outage Date : 2017-10-19

(all times Central)

Planned work (in priority order)

  1. qserv-master migration
  2. pfSense updates
  3. Dell firmware updates
  4. routine patching and reboots
  5. final verification

Affected Hosts

  • NPCF:
    • all nodes (adm01, backup01, bastion01, monitor01, object*, qserv*, sui*, verify-worker*, test0*): 0800 - 1200
    • qserv-master01: 0800 - 1600
  • (NCSA 3003: ...)

Timeline for work during this maintenance event 

Item #
Event
Planned Start
Duration
Comments
Who
1qserv-master migration0800 hrs8hprovision new hardware, move data from old server to newAndrew Loftus
2pfSense updates (NPCF)0800 hrs30mfirmware updatesSecurity
3Dell firmware updates (NPCF)0830 hrs1h
Jacob Rundall
4routine patching and reboots (NPCF)0930 hrs1h
Jacob Rundall
5final verification (NPCF)1030 hrs1.5hincludes buffer timeJacob Rundall


Pre Outage

  • Set reservation in scheduler

TBD

Outage

TBD

Rollback

TBD

Post Outage

  • Igor would like to test before unracking the old server.