(back to the list of all DMLT meeting minutes)

NOTE: For this meeting and future dates we are conducting the meeting on Blue Jeans (use web browser or below):

> Connecting directly from a room system?

> 1) Dial: 199.48.152.152 or bjn.vc
> 2) Enter Meeting ID: 293724745 -or- use the pairing code

 
> Just want to dial in? (all numbers)
> 1) Direct-dial with my iPhone or 
> +1 408 740 7256+1 408 740 7256 
> +1 888 240 2560+1 888 240 2560 (US Toll Free)
> +1 408 317 9253+1 408 317 9253 (Alternate Number)

> 2) Enter Meeting ID: 293724745

Date

Attendees

 

Goals
  • Weekly coordination meeting to discuss and resolve management items, project communications, external contacts, etc.

Discussion items

 

Item
Who
Notes
Meetings coverage this weekJeff Kantor
Kian-Tat Lim will cover Risk Review  Tuesday 10am PT
Base AE meeting on Tuesday 10am PT
Emphasize not a public space, proper doors, proper access controls
Other Tony Johnson meeting items week of May 18 at NCSA
File management
Auth/auth
Mario Juric to go to IPAC May 5 - 6, discuss SUI (side meeting with WISE on solar system objects)
SUI Visualization

Gregory Dubois-Felsmann,

Unknown User (xiuqin)

IPAC is coordinating with current UI students (John Thaler) on using Firefly components and javascripts for display configurability for Camera team.
Tatiana Goldina wil go to NCSA week of DM LT meeting and interact with students
Components are mostly reusable for DM and SDQA. Incremental SUI cost is javascripts and supporting usage.
If Camera visualization scope increase requires incremental funding, Unknown User (xiuqin) will inform Jeff Kantor, who will seek funding.

DM Leadership Team Meeting

Jeff Kantor

Agenda changes made:

Move Monday start (10:30 or later)
Moved TOWG, General Topics at NCSA
LDM-240 updatesJeff Kantor

Latest integration by Gregory Dubois-Felsmann is in docushare (leaf, not preferred version).

Data Challenges and Data ProductionsJeff Kantor
Don’t do data challenges just to do them, have a real purpose
Need to do better job of regular integration testing, recent problems with astrometry showed we are not doing enough (this is not necessarily a data challenge)
Need to plan this out far enough ahead to get into annual hardware procurement cycle
Need some “always there” compute capacity
Need to synchronize HSC and LSST stacks, this is pushing need for interim processing middleware

 Action items

REMINDER:  T/CAMs Turn in Monthly Progress Report inputs, variance reports in eCAM tool by 15th of following month