- Weekly coordination meeting to discuss and resolve management items, project communications, external contacts, etc.
Discussion items
Item | Who | Notes |
---|---|---|
Debrief of Chile meetings last week | Jeff Kantor | First stone well attended, President of Chile, US Ambassador, NSF Director, good press AMCL (especially Jim Oschman, Dave Silva, Neil Geddes) asked many questions, very positive on integration of planning between LDM-240 - PMCS - JIRA. Asked for more detailed example and some form of dashboard, due date not yet clear. Puts additional emphasis on completing LDM-240 update and integration mechanisms. LSST Corporation had discussion about assets, JK had side discussion with Pat Eliason, Robert Shelton re software under LSSTC copyright. |
DM Leadership Team Meeting | Jeff Kantor | Agenda changes: Move Monday start (10:30 or later) Move TOWG to Tuesday or Wednesday Move General Topics at NCSA to Tuesday or Wednesday Can’t do those and move Pyton/C++ to Monday, so will keep on Tuesday, TJ will attend remotely |
LDM-240 updates | Jeff Kantor | Latest integration by Gregory Dubois-Felsmann not yet in docushare, needs a few updates. T/CAMs still need to provide updates (see actions). After this iteration, we will examine dependencies, summary rows, resource loading. Goal is to have a good next cut suitable for TCT by end of DM LT May 18 - 21 F2F meeting. JK says don't use “meta-epic” names (e.g. L2 Catalog v1) or generalities ((not “improvements" to xxx), change to more descriptive milestones on milestones sheet, we will generate meta-epics (and lower level milestones) on another sheet. Remember that all columns to the right that are blank already imply improvements/enhancements. |
Data Challenges and Data Productions | Jeff Kantor | Started discussion of this in the context of higher level rows (6 - 12) of LDM-240 Time ran short, will revisit discussion next DM LT call |
Action items
REMINDER: T/CAMs Turn in Monthly Progress Report inputs, variance reports in eCAM tool by 15th of following month
- Jeff Kantor to update DMLT F2F meeting agenda from suggestions
- Frossie Economou to publish directions for handling copyright notices in NEW code (not legacy code)
- Gregory Dubois-Felsmann to produce new LDM-240 template, post to docushare as not preferred version, notify DMLT
- Jacek Becla to provide/clarify 02C.06 WBS changes for LDM-240
- Jeff Kantor to provide LDM-240 updated for 02C.07.03.02, 02C.07.03.03, 02C.09 milestones from PMCS
- Unknown User (xiuqin) to revisit FY18 - FY20 columns in LDM-240
- Simon Krughoff update for MOPS changes, work by French group on Astrometric Calibration
- Donald Petravick, Margaret Gelman to update LDM-240 02C.07 best effort now, again after additional hires made. 02C.07 rows should not be considered "commitment to deliver" on that time frame at this point.
- Jeff Kantor to publish per diem, meals provided template for those submitting TERs for Chile last week
Frossie Economou to provide LDM-240 02C.01.02 update
1 Comment
Gregory Dubois-Felsmann
LDM-240 v29 posted to LDM-240 updates, Spring 2015 page and to Docushare (non-preferred).