2pm Pacific Time
Zoom: https://washington.zoom.us/j/98846655020
attending:
regrets
- Ian Sullivan (vacation)
- Nima Sedaghat (vacation)
- John Parejko (vacation)
Topics for discussion:
- Project updates (Eric Bellm , Ian Sullivan ):
- JSR very smooth for DM–no recommendations!
- endorsed the 120s→60s prioritization
- JSR committee comment: "The committee notes that now might be an opportunity to catch up on leave or science time, and ensure the team is rested prior to the final pipeline delivery and data preview one (DP1)."
NSF approved the Operations 5yr proposal that was submitted in February. DOE is also on board with Operations long term planning, but they do not approve things for 5 years in the same way. Operations has a FY23-24 plan with DOE that is expected to continue.
- JSR very smooth for DM–no recommendations!
- USDF transition status:
- proto-support for bps over parsl
- analysis_tools sprint (all):
- Bri: wants to take a metric value to set histogram bins–looking for some pair-coding
- Erin preparing to push.
- looking for a DIASource flag
- trying to understand selector construction
- Pipelines Infrastructure (Krzysztof Findeisen , John Parejko , Brianna Smart ):
- Prompt Processing discussion tomorrow with USDF
- Krzysztof: progress on pipeline end blocked on review of sync to central repo by K-T ( - DM-35053Getting issue details... STATUS )
- Precursor processing (Meredith Rawls, Kenneth Herner , Erin Howard ):
- Ken: thinking about getting refactored diffim running even if without bps
- Image differencing algorithms, DCR ( Ian Sullivan ):
- out today
- transinet (Nima Sedaghat, Eric Bellm, John Parejko ):
- out today
- alert distribution (Eric Bellm , Brianna Smart ):
- nothing
- Review CI (https://chronograf-demo.lsst.codes/):
- no changes
- Review outstanding action items
- no change
- QA meeting in October:
- analysis_tools sprint results
- can Ian present a quick summary of the metrics/plots we've done?
- PST diffim talk: risks outline table
- Eric: fakes completeness/detection SNR discussion
- Eric thinks he needs forced photometry at the fake insertion location
- Meredith willing to pair code on it Weds.
- analysis_tools sprint results
- AOB
Action Items
Description | Due date | Assignee | Task appears on |
---|---|---|---|
| 17 Jul 2023 | Eric Bellm | AP Pipeline Meeting, 2023-06-26 |
| 11 Sep 2023 | Eric Bellm | AP Pipeline Meeting, 2023-08-21 |