Date/Time

(Default schedule is second Thursday of Month.)

ET 13:00

Meeting Online Connections:

Join Zoom Meeting
https://fiu.zoom.us/j/602918755?pwd=dmpheWkzZ0I2YWF3OGpWNzlUL3ltUT09

Meeting ID: 602 918 755
Passcode: 000000
One tap mobile
+16468769923,,602918755# US (New York)
+13017158592,,602918755# US (Germantown)

Dial by your location
        +1 646 876 9923 US (New York)
        +1 301 715 8592 US (Germantown)
        +1 312 626 6799 US (Chicago)
        +1 669 900 6833 US (San Jose)
        +1 253 215 8782 US (Tacoma)
        +1 346 248 7799 US (Houston)
Meeting ID: 602 918 755
Find your local number: https://fiu.zoom.us/u/aedBVv78VU

Join by SIP
602918755@zoomcrc.com

Join by H.323
162.255.37.11 (US West)
162.255.36.11 (US East)
115.114.131.7 (India Mumbai)
115.114.115.7 (India Hyderabad)
213.19.144.110 (Amsterdam Netherlands)
213.244.140.110 (Germany)
103.122.166.55 (Australia)
209.9.211.110 (Hong Kong SAR)
64.211.144.160 (Brazil)
69.174.57.160 (Canada)
207.226.132.110 (Japan)
Meeting ID: 602 918 755
Passcode: 000000

Meeting Recording:

TBD

Attendees

Goals

  • Coordination of networking activities across Rubin Observatory

Discussion items










  Timelines & Milestones Review

<all>

Baseline Milestones Spreadsheet Review and Checkup:

  • Cristian:  No changes in the milestones.  Approaching milestone is the end-to-end verification testing; will be working with Josh H. on that by end of the month

Documents - Google Drive


Update on CONUS Networks

CONUS Networks, including ESnet:

  • Paul:  Nothing new to report from ESnet.
  • Jeronimo:  Provisioning of colo space in ATL is under way.  The spectrum provisioning should be done by the end of the month.  Everything should be in place by May.
  • Julio:  The agreement with Internet2 on ATL ↔ JAX service is moving forward.

Chilean/International Networks Update

Developments in La Serena and end-to-end service to NCSA for upcoming Auxiliary Telescope Traffic and general (internet, mail, voice) traffic

  • Rubin (Cristian):  The Cisco ACI phaseout has been completed.  Work underway with REUNA to modify the summit-to-base connectivity, with 40x10GE being upgraded to 4x100GE.  When completed, total connectivity will be 6x100GE.  No AuxTel run this month, due to Telescope Mount Assembly work.
  • Reuna (Sergio):  Nothing new to report.

USDF - CC-IN2P3 Networks update

Mark Foster

Richard Hughes-Jones

Matt Mountz

USDF - CC- IN2P3 network:

  • USDF (Mark):  Nothing significant to report.
  • GEANT (Richard):  Nothing new to report.

Other Discussion Topics

By topic


Rubin Observatory Network Verification:

  • Cristian:  Network verification document should be released soon as LDM-570.  Testing planned by end of month.

Rubin Observatory Networks, SLAs for Operations:

  • Julio:  REUNA SLA is still pending.

Virtual NOC: 

  • Julio:  GlobalNoc quote is still valid.  Will be meeting up with GlobalNoc staff at end of month.

Document update status summary

LSE-78 :   Changes have been accepted.

LSE-479:  Work-in-progress.

O&M :   Work-in-progress.


Other businessAny



Wrap up and next meeting


Wrap up and Next meetings:  

 

All meetings at ET/1100 (subject to time changes)