This page describes the project planning process used in DM for software development.  This process is a fusion of NSF and Federal mandates for Risk and Earned Value Management and Project Planning with Agile Process.  Our nickname for this process is "Agile for Government".

Data Management Planning Process

As LSST is now in Construction and funded under the NSF Major Research Equipment and Facilities Construction (MREFC) budget, the planning process has become more formal than was the case in R&D. For the primary work plans during Construction, the following process has been used.

[[image DM Planning Flowdown]]

1. With input the flow-down of System Requirements (LSE-30) to DM System Requirements (LSE-61), LSST Program Schedules, LSST Operations plans, and a DM section of the LSST Risk Register that assesses the main programmatic and technical risks as understood at this time, a set of time-phased software capabilities and key progress metrics for the DM System has been defined. The  DM Roadmap (LDM-240) "bins" these planned software capabilities and key progress metrics into "coarse-grained" 6-month periods. These activities encompass all major DM R&D work in all areas (DM System Management and Engineering, Applications, Middleware, Infrastructure).

2. In the LSST Project Management Control System (PMCS) the DM Project Manager creates and maintains software and data release and management/system engineering project plans that encompass the entire Roadmap and add the next level of detailed work planning. In addition, the plans cover activities specific to preparing and conducting formal reviews. The granularity of the release activities in this plan are 3 to 6 months each. Each activity includes the activity description, expected start and end dates, and resources assigned. Inter-activity dependencies are also captured to allow for critical path method scheduling and analysis.  This plan is the "top-down" plan for the entire Construction phase.  It is the basis for all LSST budgets and the Earned Value Management required by the MREFC process.

3. At the start of each 6-month period (aka each new Winter or Summer Release) the entire DM team accomplishes a very detailed scoping and planning exercise to get the most detailed work plan, with individual activity granularity from 1 to 3 months.   Further, each activity is divided into steps of 2 - 20 days effort.  This plan is known as a Release Plan.  This process is done via the Agile Process, including backlog and sprint meetings, interactive communications, and design reviews.  This process is accomplished in JIRA Agile, outside the PMCS. Then plan is incorporated into the PMCS. Once work starts on the release, this level of plan is tracked on a weekly basis, and the status is rolled up to the PMCS (see DM Reporting Process below). 

The PMCS actually includes all activities to be performed during the current release period, even those that are not directly part of the data production and release (e.g. LSST and Agency Review activities, level of effort activities covering periodic meetings such as risk management meetings, etc.). While the plan includes both release and other activities, the plan is coded in PMCS so that those activities that are part of the data production and release can be easily identified in filtered views of the plan.

[[Image(DMRelease.jpg, 100%)]]

Data Management Reporting Process

The DM project (including all DM contracted institutions) is legally required to provide monthly status reports to LSST senior management, the LSSTC Board and AURA AMCL. These monthly reports are also provided to the funding agencies, and are audited annually by Federal auditors. Non-compliance with reporting requirements is cause for contract termination.

The DM project uses the following process for monthly reporting:

1. As discussed above, the DM Project Manager maintains data challenge release and management/system engineering plans in the LSST Project Management Control System (PMCS). Each activity in the plan includes the name of the activity, expected start and end dates, and assignees (with primary/lead person listed first).

2. The LSST Project provides a web-based tool for weekly status reporting against the plan. The status collected included % complete, actual and expected start and finish dates, and comments. The tool can be accessed at:

[https://www.lsstcorp.org/LSSTStatus/Login.aspx LSST Status Reporting Tool]

Instructions for the tool can be accessed via a link off the tool login page.

The standard weekly status reporting cycle is as follows:

Monday: Project Manager creates pre- and post-reschedule baselines of the plan in PMCS and publishes pdf files of the current fiscal year plans to [https://www.lsstcorp.org/primavera/ LSST PMCS Plans].

Tuesday: DM team discusses status, issues, blockages, progress.

Tuesday - Thursday: DM Project Manager updates plan with revised activities, resource assignments, etc. Project Controls Specialist fixes bugs, adds enhancements, tests, and releases new version of status tool.

Friday - Sunday: All primary resources (i.e. lead individuals) report status via the tool. This status updates the PMCS plan with the associated information.

3. The DM Project Manager exports the list of recently completed activities into tables, sorted by institution, and creates an "extended" progress report, which the DM institutional leads add narrative to. The DM Project Manager posts this report in !DocuShare. This report has been examined every year by Federal auditors to check that it shows work performed/progress by each contracted DM institution.

4. From the extended report the DM Project Manager creates a "summary report" for submission to senior management and for inclusion in the monthly report to the LSST Board and AMCL. These reports are also included in the quarterly and annual reports to the funding agencies. This summary report is also posted in !DocuShare by the DM Project Manager.

This process satisfied both Federal auditors and LSST management. However, the process has always had some issues with consistency in the plans versus data challenge release work activities as they naturally evolve during the course of development, with regularity and consistency of reporting by the team, and with the ease of "rolling up" the detailed status provided by the team to the reports and plans.

We have adjusted the status process so that we get the accuracy, consistency, and status reports/plan integration needed for Earned Value Management, which will be required during the construction phase. We are now deciding how to adjust the process, which is depicted below:

[[Image(DMReporting.jpg, 100%)]]

== Status Reporting Guidelines ==

In each status reporting Trac page, we have established "default" status milestones for various activity types:


'''Guide on Reporting Percentage Completed'''

__''For Software Design activities:''__

25% if requirements are defined;

50% if we have completed a Trac page and/or UML with design/comments

75% if we have completed a prototype implementation (if necessary)

100% if the design is reviewed and approved, ticket opened for implementation

__ ''For Software Implementation activities:''__

25% external interface defined

50% unit tests written

75% coded on branch and passes unit tests

100% code is documented, reviewed, and approved (merged to master)

__''For Software Integration activities:''__

50% packages are tagged, stack builds/runs in buildbot triggered runs (with errors)

75% packages are tagged, stack builds/runs in buildbot triggered runs (without errors)

100% packages declared and distribution-server-tagged, ready for next higher level Integration or Production runs

__ ''For other non-software, non-level of effort activities:''__

use 25% if the deliverable's specification is completed;

use 50% if the deliverable is implemented awaiting review/approval;

use 75% if the deliverable has been reviewed and is in revision;

use 100% if the deliverable is approved and posted to appropriate repository.

__''For level of effort activities:''__

% of duration elapsed is % complete

 

However, there has been some difficulty in applying these guidelines by the team, as it is sometimes the case that the process varies (e.g. unit test development occurs after initial coding). Another variation is that activities may sometimes encompass design, coding, and testing in one activity. In order to allow for these variations and improve consistency, the following guidelines are also relevant going forward:

As the Release Plan is developed, and individuals are assigned, the lead person is responsible for either adopting these milestones for that activity, or proposing another set that matches the activity at what they consider roughly 25, 50, 75, and 100% complete states. Alternatively, the activity can be subdivided into smaller activities of no more than 2 weeks, for which the states will be 0, 100% complete only. In any case, whether using the default milestones or developer-provided ones, the activities must encompass all design, development, unit test, and documentation associated with the overall activity.

In order to improve synchronization of the Release Plans in PMCS and the work as it is progressing, the plans will be revisited monthly. This allows for activities to be deferred, split, merge, emerge, etc.

 

 