In the Extra 2016 period, the International Networks and Base Site Team (WBS 02C.08) is working on projects driven by LSST inter-subsystem priorities and external-to-DM commitments.

  • Re-evaluate Summit - AURA Gatehouse fiber installation plan, baseline is on power line posts, re-examine underground along road. (Telefonica contractor, evaluating Somyl)
  • Implement 4 Gbps preliminary fiber link from Base Site to Santiago (REUNA contractor)
  • Implement 3T fiber between La Serena and Santiago and test with 10 Gbps equipment (REUNA/Telefonica contractor)
  • Continue implementation of the 2 x 100 Gbps managed ring between Santiago and Floriad (FIU/AmLight contractor)
  • Update LSE-239 Base Site Data Center Requirements and in concert with Telescope and Site team, perform cost impact analysis, support development of Base Facility bid package