Date
Attendees
Agenda
- Update on deployments
- prototype access data center hardware choices
Resources
Integration Environment Diagram
Notes
Deployments
- Cluster Services - Complete
- Nebula Expansion - Complete
- Storage Expansion - SOW complete, installation next week (Mid July)
- Verification Cluster - end of July
- Test Object Store - Next week
- Integration Environment - Purchase happening next week, end of July
Account Changes
- Designing change to move accounts to LDAP. Plan is not yet approved.
- Will take 2-3 months to complete. Limiting impact to users.
Integration Hardware
- No local Docker Hub
- Design document updated with hardware specs
- QServDB nodes sized for 500TB (Stripe82 x2 + WISE x2)