Project updates
  • AMCR report out for fact checking (nothing notable for DM).
  • A message will come out about transition to ops for AURA staff.
  • People are going back to the summit to work today.
  • Referendum on Chilean constitution expected on October 25 - possible trouble. Worries about further disruption in travel of DOE staff.
  • Comcam in the data center till January because we can't get international travels, if we could get a travel window move in November to summit (if opened)? 14 day quarantine also in place for incomers.
  • New AURA timesheet from Deltek - training this Wednesday - no truth that timecards have to be filled in daily but true no longer unreported time. [Later note: this turned out to be erroneous]. They are racing for Oct 1st but in a race. New codes with prefix. Roll out has been inconsistently communicated, Daniel has sent LSST AURA email. Previous system was home grown and the person who wrote it left long ago.
  • Focus Friday -> we need some messaging for other parts of the org, Frossie Economou drafting something for Wil O'Mullane  to review on his return.
  • Contract for the Interim Data Facility has been signed with Google. IDF spending: remember Ops activity, management request us to be clear on messaging.
DM-CCB
  • Usual issues escalated.
  • Release 21.0 is starting to be thought about. This will not be blocked by gen3.
Gen 3 middleware development
  • We have merged the rewrite of calibration handling.
  • Schema changed a lot last week (calibrations, observation reason, usage of text fields, abstract_filter rename)
  • Continuing to work through the DM-DAX-12 blocker tickets.
L2 Milestones

Test Plans due in the next 45 days

Milestones due in the next 45 days

Risks or Schedule

Risk items needing review

Overdue risks (obligation date passed)

Risk mitigations due at the end of this month

Overdue risk mitigations

 

Any other businessFrossie Economou
Nothing.
Availability

 Overdue

Due this week

Action Items

Confluence Quick Tasks

DMLT-relevant Jira Tickets