MonthMilestones & Activities
2018
Jan
Feb
  • Execute small scale test (Unknown User (aguyonnet)).
    • This test is described by DM-13401 - Getting issue details... STATUS .
    • This will demonstrate the current state state of development and provide input for upcoming milestones.
Mar
  • Deliver design documentation (Unknown User (aguyonnet)).
    • This is an update to LDM-151, or a completed version of Unknown User (aguyonnet)'s “requirements” document, which will describe the complete set of algorithms which will be delivered in August.
  • Deliver algorithmic test specification (Robert Lupton).
    • This will take the form of an update to LDM-534, or some new testing specification (see discussion on DM-11471 - Getting issue details... STATUS ) which will describe the complete set of tests which will be used to verify the algorithmic components of the pipeline.
    • These tests may rely on simulated data which will be provided by Chris Stubbs.
Apr
  • If our upcoming large scale tests require data (and particularly if they require new observations), we have to be acquiring it on this timescale.
  • By this stage, we should have some notched filter data taken on the CTIO0m9 (Chris Stubbs).
May
  • Execute large scale test #1.
    • We will execute some subset of the algorithmic test specification as a progress check.
  • Assessment of Gaia DR2 for use in providing spectral standards (LDM-151 §4.3.19).
    • We may be able to work with a French group (Nicolas Regnault?) on this; Robert Lupton will initiate discussion with them at the February 2018 DESC meeting.
Jun
Jul
Aug
  • Execute large scale test #2.
    • Demonstrate the successful operation of all pipeline algorithms (ie, take dispersed images, generate atmospheric transmission curve), not (necessarily) running within the DM stack.
    • In other words, this can be a lashed together set of scripts, but have to process realistic data and demonstrate that the algorithmic content is correct.
Sep
Oct
  • Deliver operational, tested pipeline scripts for conversion to DM standards (“stackification“)
    • These scripts should be scientifically and algorithmically complete and will have passed the August test case described above, but may not follow DM's coding, data access, etc conventions.
    • Further algorithmic refinement may occur
Nov
Dec
2019
Jan
  • Execute large scale test #3.
    • The algorithmic components of this test will be as per #2 (with any failures seen in that test now addressed).
    • This test will be run at the LSST Data Facility, using regular process execution middleware, and will demonstrate full compliance with DM stack and coding conventions.
Feb
Mar
Apr
May
Jun
  • T&SC-6800-1463: Atmospheric Telescope Ready at Summit (LSST project milestone, Feb 2018 baseline).