Date

Mar 05, 2014 @ at 9:30 PST (10:30 MST).

 

Tucson Location:  LSST Conference Room

Videocom: IP 140.252.24.8 (Direct Dial)

Call 1-866-330-1200, Participant Number 860-9352#

Attendees

  • Abi, Kem, Steve, Cathy, Srini, Francisco, Peter, George, Simon

Agenda

  1. Report of the Review Panel – everyone should read and be prepared to respond/discuss - Abi
  2. SLAC Meeting summary - use of HPC, what would it take to have code take advantage of this - Abi
  3. Cadence Workshop Planning document update - Steve
  4. JIRA Agile - Abi/Cathy
    1. Sprint 2 progress
    2. Sprint 3 assign activity for the coming week

Discussion Items

TimeItemWhoNotes
10min3Steve
5min2Abi
  • We could possibly use HPC to run opsim - Knut is our contact.
  • Need to meet to talk about current code might take advantage of this
  • SLAC could wrap and present as a web tool
70min1Abi
  • The Review Committee's report was constructive and addressed most of the issues we know about and gave a few good suggestions for moving forward.
  • An overall theme was that the work is not structured enough to ensure that deliverables needed by the Project will be completed.
  • A clear definition of what the Scheduler is, what will be delivered, and who will do the work is needed, and a document will be created to address this.
  • We already have in place some tools to help manage and track work and timelines.
  • Abi will be composing a Response to the Report, which will spell out a number of documents we will be creating to capture definitions, deliverables, prioritized lists of tasks and timelines.
5min4Cathy
  • Sprint 2 mistakenly ends March 19 instead of today; many items will carry into this week so the new end date is March 12.

New Action Items

  • Abi - compose response to Report from the Review Committee
  • George - compose response to item 7 in Report from the Review Committee and send to Abi
  • Cathy - send Heather email for status on transfer to git
  • Cathy - ask Srini and Francisco for their priorities for the coming week to add to Sprint 2
  • Francisco - write a paragraph for the Response about what it would take to make some speed improvements and identify bottlenecks in the OpSim code
  • Srini - talk to Knut to find out from SLAC to explore running OpSim code as-is on HPC.  Write up memo on results including how long it would take to execute a simulation with and without lookahead.

Old Action Items

  • Iain - review permissions for groups and users on opsimblitz1 & opsimblitz2
  • Francisco - update profile picture in JIRA
  • Srini - check into how to declare versions for SSTAR v4.0 and OpSim v3.0 in JIRA and close/release appropriately (work with Francisco)