Meeting Notes and Assigned Tasks
Attendees: Kem, Cathy, Srini, Steve, Francisco, Lynne, Abi
Review Planning
- George/Andy - fill out and submit Review Plan
- Cathy - update OpSim DataAccess Page for reviewer use (defer until after Dec)
Rolling Cadence
- Next steps on developing the v3.x OpSim codebase will be to work on the Rolling Cadence capability.
- Francisco's first priority is documentation/presentations for the review, then transition to this.
- Steve will draft a description of the desired functionality and boundaries and iterate with Kem
Verification of v3.0
- Cathy will take a more detailed look at how the weather implementation has been changed since v2.3.2
- Cathy will start a design/design run with standby as a fiducial run
OpSim v3.0 - Release by Wed, Dec 18
- Kem - OPSIM-39: Edit default proposal files and parameters in LSST.conf
- Kem - astronomicalsky.conf - not caching temporal; now in schedulingData.conf (+other?)
- Kem - Remove conf files that are obsolete; and parameters that are no longer used - recalcskycount, reuserankingcount in each prop ; leaving in Scheduler.conf; delete useLookAhead
- Cathy - Validation (should be encompassed by existing runs, but do one complete comparison run)
- Francisco - Release OpSim v3.0 & install on production machines
SSTAR v4.0 - Release by Wed, Dec 18
- Cathy - validate SSTAR v4.0 (include final v3.0 run)
- Srini - Release SSTAR v4.0 & install on production machines
- Fixing Aitoff plots for WLProp confs with more than one sequence will be addressed in MAF
Documentation - Second draft due by Dec 18 for circulation internally
- Abi - Overview **
- Francisco - Simulator description **
- Francisco - Simulator requirements
- Francisco - Conceptual APIs for the for the Scheduler (interface with OCS)
- Srini - Sphinx documentation on SSTAR *
- Srini / Kem - Sphinx documentation on OpSim * (Kem to send text to Srini)
- Srini - Post-processing tools: SSTAR+
- Steve/Srini - Post-processing tools: Metrics
- Steve/Lynne/Srini - MAF design and development plan
- Cathy - Validation v3.0 [Cathy]
- Kem/Cathy - Baseline run like opsim3.61
(** denotes first priority; * denotes second priority)
Meeting Announcement and Agenda
We will meet tomorrow, Wednesday to resume our weekly meetings at 9:30 PST / 10:30 MST.
Tucson Location: LSST Conference Room
Videocom: IP 140.252.24.8 (Direct Dial)
Telecom: 1-866-330-1200 Participant Code 860-9352#
Agenda and notes also published on Confluence:https://www.lsstcorp.org:8443/display/SIM/11+Dec+2013+Meeting
I am copying my to-do list from our meeting last week at the FDR that can serve as an agenda.
Tasks
- Abi - fill out and submit Review Plan
- Cathy - DataAccess Page - emily
OpSim v3.0
- OPSIM-7: Scheduler.conf and SchedulingData.conf key values not stored in the DB
- OPSIM-39: Edit default proposal files and parameters in LSST.conf
- Remove conf files that are obsolete; and parameters that are no longer used - recalcskycount, reuserankingcount in each prop ; leaving in Scheduler.conf; delete useLookAhead
- OPSIM-59: For sequence proposal DDcosmology1.conf (e.g. opsimblitz1.1053) number of visits only works for u , not grizy (deferred to v3.x)
- OPSIM-60: Materialize output tables in OpSim databases (defer)
- OPSIM-61: Clean up src directory tree removing unused python modules
- OPSIM-xx: Nested subsequences doesn't work (defered)
- OPSIM-xx: move important params from Universal configs bottom to top of file (defer)
- Testing - unit tests (complete?)
- Validation (should be encompassed by existing runs, but do one complete comparison run)
- Release OpSim v3.0 & install on production machines
SSTAR v4.0
- OPSIM-53: summaryreport SQL queries taking too long (defer to 4.x)
- complete nested sub-sequence run [Kem] (defer to 3.1)
- run SSTAR on that run [Srini]
- modify SSTAR code if necessary [Srini]
- modify OpSim code if necessary [Kem]
- repeat or move on to validation
- validate SSTAR v4.0 (include final v3.0 run) [Cathy]
- Release SSTAR v4.0 & install on production machines [Srini]
Documentation
- Simulator requirements [Francisco] (see below) Srini to send docushare link-
- Overview [Abi] **
- overview of how we are doing what we are doing - overarching philosophy why a tool, why this form, why not someone else's code?
- motivate scheduler AND simulator
- Include or refer to requirements document [Francisco]
- structure of how the models are broken out and
- logical flowchart of decision making
- point out various functions at different times of the project
- Simulator description ** - How does it actually work - (technical journal article, refer SPIE paper - based on this and different in these ways…) [Francisco]
- Conceptual APIs for the for the Scheduler (interface with OCS)
- but don't turn into a review of what it is going to become
- framework in which we are going to test the new scheduling algorithms
- API between simulated scheduler and actual scheduler
- what streams and what information needs to be exchanged (not precise interfaces)
- Sphinx documentation on SSTAR *(how to install, run, what comes out) [Srini]
- Sphinx documentation on OpSim * (how to install, change parameters, output) [Srini]
- overview incl Francisco how the code works reference
- Post-processing tools: SSTAR+ (explains) + other output (validates code; annotate sample SSTAR) [Srini]
- Post-processing tools: Metrics (SSTAR+ doesn't do it all, need other science cases; give examples of 7- reshape PST) now need MAF so… [Steve/Srini]
- MAF design and development plan [Steve/Srini] (Present the MAF code design for approval)
- maybe just the requirements (or proposed requirements) (include Lynnes && Steves??)
- use cases -
- architectural design
- maybe prototype class designs
- need to have it done by may for workshop (June
- Validation v3.0 [Cathy]
- Cadence runs [Kem - defer to after review?]
- Baseline run like opsim3.61 - reference run? [Kem] -