This page summarizes the first Operations Rehearsal (the purpose and intended content are outlined in LDM-643) which took place May 7-9, 2019.
Night 1: (May 7, 2019)
5:30am: Data transfer from the Base to LDF initiated (nominal transfer rate shows as ~2 Mbyte/s)
10:00am: Switched to backup of nightly data to facilitate processing prior to meeting.
11:00am: Initiated processing campaign (singleFrameDriver.py)
11:48am: Processing campaign completed (222 rafts processed in 48 min using 24 core x 3 nodes).