Jeff Kantor available remotely at certain times, I am in Florida Jan 6 - 13, at South American Astronomy Coordination Committee (SAACC) networks meeting Jan 10 - 11
Jim Bosch (arrive Monday ~7:30pm, leave Friday ~9am)
Finishing and maintaining design documents (especially LDM-151): how worthwhile is effort to polish these and make them scientist-readable (and up-to-date)?
Discoverability of and all-team access to documentation; accessibility of mature drafts (related to the above)
Topics of interest to T/CAMs:
Integration & test, Commissioning: Effort and schedule for DM verification and system verification
Data Challenges: What are we doing when?
Related: Future of PDAC?
Simulated data:
Some was generated for DESC, Euclid but we haven't seen it; is it useful for us?
What about list of simulated data desires sent to Sims group at the last JTM?
Binary distributions: answers to questions in Tim's e-mail.
We have risks associated with specific WBSs but currently have no interaction between T/CAMs and the people reporting on risks. Closer integration of per-WBS risks with system engineering is desired to more accurately reflect current status.
Pipeline QA functionality definition discussions. Is it the precursor for commissioning support?
KPMs - this work is orphaned in the short term - are we still committed to doing release characterisations?
09:00 What the project manager expects (20min)- Victor
09:30 Overview of plan status (20min)- Mario
10:00 Individual TCAM views on the plan specifically
15-20 mins max
A single slide presenting the main milestones (10km view) - many of whihc may be the dependencies of other teams
Overview of dependencies and timing ... Dependency spreadsheet giving all milestones between teams, synchronized with the plan shoudl be avialble refer to issued document
Rolled up overview of resources -... Detailed planning packages (in a variety of tools) with resource estimates for each team should be available refer to issued document
Narrative description of potential descopes involving each team with order-of-magnitude estimates for impact
10:00 Alerts - Simon
10:25 Data Release Production - John Swinbank
10:50 Break
11:05 Data Access Services - Fritz
11:30 SUIT - Xiuqin Wu
11:55 SQuaRE - Frossie Economou
12:30 LUNCH
14:00 Production, Infrastructure and Ops - Margaret
14:25 Open discussion with Victor
15:00 Break
15:15 Actions for finalizing the plan and scheduling Day #3 work (Victor/wil/Mario)
16:00 Documentation
17:00 End
Day #3: Jan 12 (Main Conference Room)
09:00-17:00 Meetings with Wil and time for work determined to be urgently needed in discussions from Days #1 and #2