Use of Cloud Infrastructure .. further study needed ?
Topics of interest to T/CAMs:
Integration & test, Commissioning: Effort and schedule for DM verification and system verification
Data Challenges: What are we doing when?
Related: Future of PDAC?
Simulated data:
Some was generated for DESC, Euclid but we haven't seen it; is it useful for us?
What about list of simulated data desires sent to Sims group at the last JTM?
Binary distributions: answers to questions in Tim's e-mail.
We have risks associated with specific WBSs but currently have no interaction between T/CAMs and the people reporting on risks. Closer integration of per-WBS risks with system engineering is desired to more accurately reflect current status.
Pipeline QA functionality definition discussions. Is it the precursor for commissioning support?
Draft Agenda
Day #1:JAN 10 - start 9:30 ?
Introduction of Wil to the team - revisit the Good/Bad/Ugly talk from LSST Europe.
What is our goal: designing the DM mission statement
Discuss Agile with Wil and how we can tune it for LSST
AGILE on Gaia talk (orginally for ESOC) to focus the discussion
Added to that how Gaia SOC moved to OPS from AGILE dev
Individual/Team intros and how each do Agile
perhaps 15 minutes per team
what experiences you have had
what problems you have had
suggstions to improve the Agile process
Day #2:Jan 11
Where we are with the replan (reasonably final by this day)
Each team present briefly their part of the plan, interdependancies, and possible descope or delay to later phase
A few slides at 10km of each team's roadmap
Dependency spreadsheet giving all milestones between teams, synchronized with the plan
Detailed planning packages (in a variety of tools) with resource estimates for each team
Narrative description of potential descopes involving each team with order-of-magnitude estimates for impact
TBD topics, 1:1s
Day #3: Jan 12
TBD topics, 1:1s
For 1:1 meetings please ask Libby to add to my diary.