Infrastructure meetings take place every Thurs. at 9:00 Pacific on the BlueJeans infrastructure-meeting channel: https://bluejeans.com/383721668 . (changed to every Thursday in July 2019)
Date September 5, 2019
Attendees Kian-Tat Lim Fritz Mueller Michelle Butler
Simon Krughoff
Igor Gaponenko
Discussions Item
Who
Notes
Item
Who
Notes
Items from MichelleB about infrastructure Power outage for all of LSST. starting 9/27 at 10PM PT and gong until 9/28 6PM PT Jumbo frames testing didn't get very far. Will be a focus for the LSP in the next week. FY2020 submitted and approved. For the people attending this meeting; there will be some new K8 nodes added and a small Qserv for the "stable" side of the LSP In the process of ordering the commissioning environment for the base. add on items
Action items: