(This page should ultimately be replaced by a JIRA query against the envisioned future JIRA reimplementation of the change request database, using labels to represent "DM is interested in this". At the moment it is manually maintained.)
This page is manually maintained (primarily by Gregory Dubois-Felsmann and Tim Jenness). It contains change requests originated by DM as well as ones from or affecting other LSST subsystems which the editors believe will be of interest to DM staff. It also omits certain manifestly DM-related change requests that are primarily concerned with PMCS technicalities and will not be subject to full CCB action. These change requests are always available by querying the database for DM-originated requests. The editors welcome comments on this policy!
Principal references:
- LSST Change Request database
- Query for change requests originated by DM (note that this will not capture all the requests in the table below)
- LSST Change Control Process, LPM-19
LCR | Title | State | Documents Affected | Summary and comments | Related Issues | CCB meeting for decision |
---|---|---|---|---|---|---|
LCR-1214 | Clarify DM's Level 1, 2, and 3 Terminology for the Science Community | APPROVED | LSE-163, LPM-231 | |||
LCR-1203 | Searchable - Interactive Nightly Reports | STUDIED | Need to determine what DM will need to do to meet this requirement. | |||
LCR-1154 | Stand Up Data Access Rights Working Group - Put LPM-221 under Change Control | FULLY IMPLEMENTED | LPM-221 | |||
LCR-1070 | DM Milestones for Base LAN and Summit Network | FULLY IMPLEMENTED | ||||
LCR-1068 | Revised Commissioning Plan LSE-79 | FULLY IMPLEMENTED | LSE-79 | |||
LCR-1065 | Date Update for the DM/EPO ICD Phase 3 Milestone | FULLY IMPLEMENTED | ||||
LCR-1064 | Add Priorities to LSE-61 | FULLY IMPLEMENTED | LSE-61 | |||
LCR-1048 | Update Summit Network Installation Schedule | FULLY IMPLEMENTED | ||||
LCR-1034 | Auxiliary Telescope Spectrograph Instrument and Detector Schedule and Cost Update | FULLY IMPLEMENTED | Updates the schedule and cost of the procurement of the Auxiliary Telescope Spectrograph Instrument. Details of the change are not yet available (). | |||
LCR-1024 | Tie LSE-163 into OSS | APPROVED | LSE-30 (OSS); others indirectly, LSE-61 | Resolves a long-running formal gap in our requirements flowdown. Makes the contents of the DPDD (LSE-163) authoritative in deriving DM-level requirements (i.e., in the DMSR, LSE-61) by stating in the OSS that the data products generated by DM shall conform to the DPDD. | ||
LCR-1021 | Adjust Dates for DWDM Equipment Installation | FULLY IMPLEMENTED | PMCS | Notes ~60 day delay in the installation of the Summit-Base and Base-Santiago DWDM equipment, triggered by late delivery from the equipment vendor. New schedule shows installations complete by roughly November 2017. | ||
LCR-1018 | Follow up to New Camera Image Types (LCR-773) to flow down requirements to subsystem specs and ICDs | APPROVED | LSE-59, LSE-71; DM impact to be analyzed | Adds the new image types introduced by LCR-773 (New Camera Image Types) to the Camera requirements and OCS-Camera ICD. Superficially this doesn't require a response in DM-level documents; however, the exploitation of the new image types is driven by calibration requirements and so most likely they should eventually appear in DM documents. Note that as of LCR-773 itself is Approved but not Fully Implemented. | ||
LCR-1013 | Place the LSST Science Platform Vision Document under Change Control | FULLY IMPLEMENTED | LSE-319 | |||
LCR-1006 | Update DM-OCS ICD, LSE-72, to reflect DM design changes and to match recent LSE-70/LSE-209 | STUDIED | LSE-72, LDM-230 | Updates LSE-72 to match current design work. Incorporates changes from LCR-780 and LCR-888. | ||
LCR-1005 | LSE-209 Software Component Document Reformat and Reqs Refresh | REJECTED | LSE-209, likely LSE-72 | This is mostly a cleanup pass on a key OCS middleware definition document. The DM-to-OCS interface depends on its contents, so it's likely that some consequential changes to LSE-72 will be needed. | ||
LCR-1004 | Withdraw LSE-77, "Infrastructure Interfaces Between Data Management and the Base Facility" | FULLY IMPLEMENTED | LSE-77, possibly LSE-239 | In 2015, the project shifted from the then-existing DM-to-T&S ICD LSE-77 to a new "Base Data Center Requirements" document, LSE-239, to capture the needs of DM for data center space at the Base. LSE-77 became effectively a dead letter in the process. This change request is intended to just clean that up. Final result: LSE-77 has been withdrawn. | Vote initiated | |
LCR-983 | Integrate DM and Camera Data Systems Early | STUDIED | PMCS, possibly ICDs | Perform additional early integration activities, notably around the use of the CCOB camera test facility to generate data to be ingested into DM on a regular basis. | ||
LCR-974 | Update Network Requirements in LSE-61 | FULLY IMPLEMENTED | LSE-61 | One new requirements, modifications to 3 others. | ||
LCR-964 | Summit Computer Room Requirements Document | FULLY IMPLEMENTED | LSE-299 (new) | Consolidates all planned compute hardware needed on the Summit (except what is actually in the domes). | ||
LCR-963 | Summit - Base ITC Design Document | FULLY IMPLEMENTED | LSE-309 (new) | Product of Jeff Kantor's Summit-Base Tiger Team Touches on almost all DM's interfaces with the other systems. | ||
LCR-962 | Flowdown LSE-163 (DPDD) to LSE-61 (DMSR) | FULLY IMPLEMENTED | LSE-163, LSE-61 | Includes a handful of unrelated requirements changes/additions. Some text updates to DPDD. | ||
LCR-943 | Minor updates to LSE-63 | FULLY IMPLEMENTED | LSE-63 (Data Quality Assurance Plan) | LSE-63 has not been updated since 2011. This update includes some minor modernizations based on current best practice and removes mention that we are currently in R&D phase. | ||
LCR-924 | Duplicate LSR Data Performance Metrics in OSS for DM Flow Down | APPROVED | LSE-30 (OSS) | |||
LCR-921 | DM to Provide Service for Publishing Predicted Visit Sequence | FULLY IMPLEMENTED | LSE-61 (DMSR) | |||
LCR-908 | Keep all Data Releases loaded in databases | APPROVED | LSE-30 (OSS) and many subordinate documents | Adopt the following requirement: "The LSST project shall maintain user access to the contents of all Data Releases. This facility may be provided with reduced performance and capacity for Data Releases older than the most recent one, but be qualitatively identical otherwise." in place of the current policy of maintaining access only to the two most recent data releases. | - RFC-325Getting issue details... STATUS | |
LCR-900 | DM S17 Mid Cycle Replan | FULLY IMPLEMENTED | (PMCS) | Implement S17b plans for NCSA, SQuaRE, and AP with some small tweaks to other subsystems. | ||
LCR-899 | Scheduler Requirements Control | STUDIED | LTS-347, possibly LSE-62 | Promote the scheduler requirements in LTS-347 to project-level change control, moving them to an LSE-* document. | ||
LCR-888 | Proposed Meta-data header client for LSST images | APPROVED | LSE-72, LDM-230, probably numerous others | Proposes that a common Summit-Base service be created that extracts all observation metadata (from published telemetry or the EFD) intended to be packaged with the image files, storing an artifact containing all this metadata as "headers" for later retrieval. | Q: Does this have anything to do with the reformatted EFD database? -XW | |
LCR-851 | Update to LSE-151 | FULLY IMPLEMENTED | LSE-151 "Interface Control & Compliance Management Process" | Clarifies language surrounding ICDs and documents that describe or actually are the implementations of the interfaces controlled by ICD. | 2017-02-22 | |
LCR-849 | Update LSE-78 LSST Observatory Network Design | FULLY IMPLEMENTED | LSE-78 | LCR-849 is to make LSE-78 consistent with and refer to the Network Sizing document LDM-142. Requested CCB if this can be voted on via the electronic voting process. I think it is non-controversial and was discussed at some length in the DM TCT when we last updated LDM-142. It would be good to get this done, as there are a number of more significant changes to the same documents coming very soon as a consequence of Tiger Team activities. | 2017-03-05 email vote | |
LCR-838 | Auxiliary Telescope Scheduler | LCR ASSIGNED | LTS-187 (draft: SPT-372) | |||
LCR-836 | Typographic correction to LSE-69 to match LSE-130 | APPROVED | LSE-69 | - DM-9336Getting issue details... STATUS | 2017-02-22 | |
LCR-835 | Camera Heterogeneous Sensor Focal Plane | FULLY IMPLEMENTED | Implicitly sharpens requirements on ability to determine the correct pixel geometry upon data ingest from Camera to DM. May have an implication for the generation of difference imaging templates, at the (~annual) template-creation level and/or at the nightly template-warp-instantiation level. | 2017-03-22 (status check only) | ||
LCR-795 | Updates to DM/EPO interface requirements (LSE-131) | FULLY IMPLEMENTED | LSE-131 | See substantive discussion in the DM Leadership Team Meeting 2017-03-20. | 2017-03-22 (vote deferred) | |
LCR-788 | Transfer Task Framework from 02C.07 to 02C.06 | FULLY IMPLEMENTED | (PMCS) | Moves the Task class and a cluster of related classes and interfaces to be a responsibility of the SLAC group. | ||
LCR-787 | Commissioning Re-Plan 2016 | FULLY IMPLEMENTED | LSE-79 | See also the February 2017 Commissioning Review. Awaiting the report of the review committee. | ||
LCR-786 | Eliminate Base Network Outage Buffer; Expand Summit Camera Image Buffer | FULLY IMPLEMENTED | Unclear | Kevin Long is awaiting guidance on what WBS element to use for the additional budget for the enlarged buffer. The "documents affected" is "Unclear" because it has not been completely decided whether to implement this as a change to requirements or as a specification that exceed the requirement. This is a separate question both at system and at Camera level. | ||
LCR-785 | Observatory Operations Server | REJECTED | Unclear; may require a new ICD. Would also affect DM design documents. | |||
LCR-783 | Commissioning Cluster Services | REJECTED | Appears in DM design documents | |||
LCR-782 | Additional OCS Driven Services for Archive Center Access | APPROVED | LSE-72, possibly LSE-140 | Provide a means for the OCS to launch predefined batch processing actions at the Archive Center. Likely to be used for, e.g., producing synthetic calibration images following the collection of the input flats, bias frames, etc. | ||
LCR-780 | Eliminate Engineering & Facilites Database Copies in Offline Archive Centers | APPROVED | LSE-72, LDM-230 | Requires changing EFD interface with OCS to be the ingest to the Reformatted EFD. : discussed at an OCS-DM meeting. Further discussions planned for . | ||
LCR-773 | New Camera Image Types | FULLY IMPLEMENTED | LSE-30 (OSS) | Adds requirements for a pinhole filter and for the capability to take filterless images. | ||
LCR-747 | Unified LSST Authentication and Authorization Services | FULLY IMPLEMENTED | LSE-279 | Provides unified authentication and authorization technical services to assure authorized individuals access LSST services and systems. | 2017-10-19 minutes | |
LCR-733 | LSST CCD, CCS, and DAQ for the Auxiliary Telescope Spectrograph | FULLY IMPLEMENTED | LSE-140 and many others | Requires consequential changes to LSE-140 because of the change to direct spectrograph-to-DM image retrieval. The details of the timeline of capabilities required of DM to support the spectrograph, starting 8/2018, remain under analysis. | ||
LCR-687 | Alternate Standard Visit with 30s single exposure | FULLY IMPLEMENTED | LSE-29 (LSR), LSE-30 (OSS) | Requires that DM be able to handle two types of standard visits: two 15s exposures, or one 30s exposure. Somewhat vague on the question of how closely the two types of visits could be interleaved. | 2016-11-16 minutes | |
LCR-586 | Update LSE-209 Software to OCS ICD | APPROVED | LSE-209 | A further round of technical updates to the OCS-to-subsystem device interface. The draft already serves as the basis for the prototype and early integration work that is ongoing. | 2017-03-22 | |
LCR-581 | Calibration Hardware Requirements Update | FULLY IMPLEMENTED | LSE-30 (OSS), LSE-60, LSE-140 (DM ICD) | |||
LCR-458 | Support for "Deep Drilling" observing scenario | PENDING |