Date

Attendees

Goals

  • Review readiness to begin assembling the system

Discussion items

TimeItemWhoNotes
 NCSA statusUnknown User (jalt)
  • Hardware availability
    • Everything is up, everyone has access
    • ssh scripts sent around
  • Disk mounts, RAID, and other configuration
    • GPFS has now been added to the DAX nodes
    • Not sure whether requested RAID configuration has been set up yet
  • "pdac" label added to all relevant PDAC JIRA items by Joel Plutchak
 SLAC statusIgor Gaponenko
  • Data availability and copying
  • Progress on attempting to install Qserv, run services on PDAC
 IPAC statusUnknown User (xiuqin)
  • Readiness for attempting to run a server on PDAC hardware
  • Portal definition progress
 PlanningGregory Dubois-Felsmann 

Action items

(See the Prototype Data Access Center work items page for a summary of past action items)

  •  