This page details the SOCS workplan with planned and actual storypoints.
Updated: 2015-10-27 16:05
SOCS Release v0.1
Release Date: 2015-09-30
Statement of Work
- Release OpSim Requirements document
- Design SOCS independant of OpSim
- Define and initiate SOCS code modules in SE Simulations repository
- Prototype and benchmark Communications using current release of DDS-SAL-Python
OpSim Requirements Document
Planned Story Points = None
Statement of Work
- Write OpSim requirements document
- Ensure Scheduler requirements document reflects necessary interface
Issues
Number of Issues = 10
Key | Description | Status | Story Points |
---|---|---|---|
SIM-1274 | Ensure requirements are captured in both documents | Done | 4.0 |
SIM-1273 | Arrange and hold meeting to review Scheduler Requirement doc. | Done | 3.0 |
SIM-1272 | Coordinate creation of diagram & narrative with Francisco | Done | 3.0 |
SIM-1270 | Add text from Sphinx on DB Architecture to Appendix C | Done | 1.0 |
SIM-1269 | Add text for configuration tables to Appendix B (parameters) | Done | 4.0 |
SIM-1243 | Update OpSim short term work plan | Done | 4.0 |
SIM-1191 | Draft 6month development plan for Scheduler coordinating with OCS | Done | 1.5 |
SIM-1190 | Draft 6month development plan for Scheduler coordinating with OCS | Done | 1.5 |
SIM-1086 | Draft of Epics / Issues for Obsim/Scheduler Dev plan & review backlog | Done | 0.5 |
SIM-1085 | Draft of Epics / Issues for Obsim/Scheduler Dev plan & review backlog | Done | 0.5 |
Design and Prototyping for SOCS
Planned Story Points = None
Statement of Work
- Create repository for new SOCS code
- Create repository for DDS testing scripts
Issues
Number of Issues = 2
Key | Description | Status | Story Points |
---|---|---|---|
SIM-1246 | Collect scripts for DDS tests | Done | 4.0 |
SIM-1245 | Create repository for sims_ocs | Done | 2.0 |
SOCS Release v0.2
Release Date: 2015-12-27
Statement of Work
- Implement SOCS structure with interface
- Implement simulation kernel with time simulator
- Refactor and integrate observatory model
- Implement observatory telemetry simulator
- Implement simulation sequencer with targets handling
- Refactor and integrate observations DB
- Integrate with Scheduler
- SOCS topics: telemetry for time and observatory conditions
- Scheduler topics: next target from scripted proposal
Implement SOCS interface structure
Planned Story Points = 25.0
Statement of Work
- SAL communication layer
- Driver scripts
- Configuration parameter system
- DB interaction layer
Issues
Number of Issues = 4
Key | Description | Status | Story Points |
---|---|---|---|
SIM-1484 | Create initial driver for simulation | In Progress | 1.0 |
SIM-1483 | Setup initial configuration system | In Progress | 1.0 |
SIM-1451 | Create parser and logging infrastructure | Done | 1.0 |
SIM-1395 | Remaining Story Points | To Do | 25.0 |
Implement SOCS Simulation Kernel
Planned Story Points = 13.0
Statement of Work
- Implement Time Handler interface
- Implement Time Handler communication via DDS topics
- Implement Sequencer interface
- Implement Sequencer behavior for DDS topics on requested targets
- Implement Sequencer behavior for handling observations
- Implement Sequencer communication of observations (visits) via DDS topics
- Implement DB interaction for recording visit information
Issues
Number of Issues = 4
Key | Description | Status | Story Points |
---|---|---|---|
SIM-1532 | Implement initial sequencer behavior | In Progress | 5.0 |
SIM-1531 | Implement initial time handler behavior | In Progress | 3.0 |
SIM-1530 | Implement initial simulation driver class | In Progress | 2.0 |
SIM-1397 | Remaining Story Points | To Do | 13.0 |
Integrate and test with Scheduler v0.2
Planned Story Points = 19.0
Statement of Work
- Checking ability to run Scheduler from SOCS driver
- Checking observatory telemetry communication between SOCS/Scheduler
- Checking observation (visit) telemetry communication between SOCS/Scheduler
Issues
Number of Issues = 2
Key | Description | Status | Story Points |
---|---|---|---|
SIM-1533 | Test time handling and observation communication | In Progress | 3.0 |
SIM-1398 | Remaining Story Points | To Do | 19.0 |
Implement SOCS Observatory Model
Planned Story Points = 19.0
Statement of Work
- Inherit from Scheduler Observatory Model
- Implement interface for variational model
- Implement observatory telemetry broadcast via DDS topics
- Implement configuration parameter handling
- Implement DB interaction for state record keeping
Issues
Number of Issues = 1
Key | Description | Status | Story Points |
---|---|---|---|
SIM-1396 | Remaining Story Points | To Do | 19.0 |
Implement production tools v0.2
Planned Story Points = 51.0
Statement of Work
- Design layout of post-processing reorganization
- Create new repo and structure for tools
- Refactor the current conversion tools
- Implement functionality needed from v0.2 of SOCS
- Setup structure for production pipeline
Issues
Number of Issues = 6
Key | Description | Status | Story Points |
---|---|---|---|
SIM-1540 | Make changes in m5 calculation in modifySchema.sh | To Do | 3.0 |
SIM-1538 | Production Scripts: Complete running version of launch script. | In Progress | 2.0 |
SIM-1537 | Production Scripts: Complete the identification of all steps needed in the process with placeholders | Done | 2.0 |
SIM-1535 | Provide consulting on production pipeline scripts | In Progress | 1.0 |
SIM-1438 | Design & initial implementation of scripts for production pipeline | Done | 8.0 |
SIM-1400 | Remaining Story Points | To Do | 51.0 |
Cadence Studies v0.2
Planned Story Points = 42.0
Statement of Work
No description provided.
Issues
Number of Issues = 6
Key | Description | Status | Story Points |
---|---|---|---|
SIM-1542 | Refine rolling cadence to count visits in the desired way. | To Do | 5.0 |
SIM-1541 | Support cadence science runs | In Progress | 2.0 |
SIM-1539 | Reconfigure OpSim text/links for new public website page under Simulations | Done | 2.0 |
SIM-1399 | Remaining Story Points | To Do | 42.0 |
SIM-1081 | generate and analyze permutations of reference runs with various auxiliary proposals | In Progress | 3.0 |
SIM-957 | Reference Run: Prepare written documentation and package for Change Control Board | In Progress | 2.0 |
SOCS Release v0.3
Release Date: 2016-05-20
Statement of Work
- Refactor and integrate Astronomical Sky
- Integrate Observatory Model slew and track behavior for observing visits
- Implement observing behavior in simulation sequencer
- Integrate DB storage of targets received and visits performed
- Integrate and benchmark performance with Scheduler
- Test multiple AD proposals survey with slew time cost and sky brightness
- Test repeatability
- Test speed under simulation
Implement SOCS Astronomical Sky
Planned Story Points = 19.0
Statement of Work
- Assist Scheduler developer in using sims_skybrightness package for Scheduler classes
- Inherit from Scheduler classes
- Implement interface for variational model
- Implement sky conditions telemetry broadcast via DDS topics
- Implement configuration parameter handling
- Implement DB interaction for record keeping
Issues
Number of Issues = 1
Key | Description | Status | Story Points |
---|---|---|---|
SIM-1401 | Remaining Story Points | To Do | 19.0 |
Enhancements for Observatory Model
Planned Story Points = 13.0
Statement of Work
- Implement slewing and tracking behavior to simulate a visit
Issues
Number of Issues = 1
Key | Description | Status | Story Points |
---|---|---|---|
SIM-1402 | Remaining Story Points | To Do | 13.0 |
Enhancements for Sequencer
Planned Story Points = 13.0
Statement of Work
- Add communication between Sequencer and Observatory Model for visit
- Implement DB interaction for visit record keeping (targets and observations)
Issues
Number of Issues = 1
Key | Description | Status | Story Points |
---|---|---|---|
SIM-1403 | Remaining Story Points | To Do | 13.0 |
Implement Proposal Interface
Planned Story Points = 25.0
Statement of Work
- Work with stakeholders to help Scheduler developer define necessary behavior
- Implement configuration parameter passing via DDS topics
Issues
Number of Issues = 1
Key | Description | Status | Story Points |
---|---|---|---|
SIM-1404 | Remaining Story Points | To Do | 25.0 |
Integrate and test with Scheduler v0.3
Planned Story Points = 23.0
Statement of Work
- Ensure that SOCS/Scheduler still work together
- Initial benchmarking of SOCS/Scheduler performance
- Begin testing repeatability of SOCS/Scheduler system
Issues
Number of Issues = 1
Key | Description | Status | Story Points |
---|---|---|---|
SIM-1405 | Remaining Story Points | To Do | 23.0 |
Cadence Studies v0.3
Planned Story Points = 52.0
Statement of Work
No description provided.
Issues
Number of Issues = 1
Key | Description | Status | Story Points |
---|---|---|---|
SIM-1406 | Remaining Story Points | To Do | 52.0 |
Implement production tools v0.3
Planned Story Points = 56.0
Statement of Work
Continued work on Production tools
Ensure post-processing tools work
Begin exercising production pipeline
Develop any new MAF metrics for SOCS/Scheduler validation
Issues
Number of Issues = 1
Key | Description | Status | Story Points |
---|---|---|---|
SIM-1407 | Remaining Story Points | To Do | 56.0 |
SOCS Release v1.0
Release Date: 2016-10-27
Statement of Work
- Refactor and integrate Environment Model
- Simulate weather telemetry, clouds and seeing
- Incorporate filter swaps during new moon
- Incorporate downtime simulator
- Implement Scheduler configuration via commands
- Integrate with Scheduler
- Test with complete survey
- Test repeatability
- Test execution speed
Simulate weather telemetry, clouds and seeing
Planned Story Points = 20.0
Statement of Work
No description provided.
Issues
Number of Issues = 0
Incorporate filter swaps during new moon
Planned Story Points = 9.0
Statement of Work
No description provided.
Issues
Number of Issues = 0
Incorporate downtime simulator
Planned Story Points = 15.0
Statement of Work
No description provided.
Issues
Number of Issues = 0
Implement Scheduler configuration via commands
Planned Story Points = 20.0
Statement of Work
No description provided.
Issues
Number of Issues = 0
Integrate and test with Scheduler v1.0
Planned Story Points = 23.0
Statement of Work
No description provided.
Issues
Number of Issues = 0
Refactor and integrate environmental model
Planned Story Points = 15.0
Statement of Work
No description provided.
Issues
Number of Issues = 0
Cadence Studies v1.0
Planned Story Points = 57.0
Statement of Work
No description provided.
Issues
Number of Issues = 0
Implement production tools v1.0
Planned Story Points = 68.0
Statement of Work
No description provided.
Issues
Number of Issues = 0
SOCS Release v1.1
Release Date: 2017-04-18
Statement of Work
- Support for previous release
- Support Development for Area Distribution Look Ahead in Scheduler 1.1
- Implement non deterministic weather simulator
- Implement non deterministic downtime simulator
- Integrate and test with Scheduler
- Test survey with Area Distribution proposals and Look Ahead
- Test speed performance
- Test repeatability
Support Development for Area Distribution Look Ahead in Scheduler 1.1
Planned Story Points = 12.0
Statement of Work
No description provided.
Issues
Number of Issues = 0
Implement non-deterministic weather simulator
Planned Story Points = 47.0
Statement of Work
No description provided.
Issues
Number of Issues = 0
Integrate and test with Scheduler v1.1
Planned Story Points = 12.0
Statement of Work
No description provided.
Issues
Number of Issues = 0
Implement non-deterministic downtime simulator
Planned Story Points = 12.0
Statement of Work
No description provided.
Issues
Number of Issues = 0
Cadence Studies v1.1
Planned Story Points = 62.0
Statement of Work
No description provided.
Issues
Number of Issues = 0
Implement production tools v1.1
Planned Story Points = 74.0
Statement of Work
No description provided.
Issues
Number of Issues = 0
SOCS Release v1.2
Release Date: 2017-08-24
Statement of Work
- Support for previous release
- Support Development for Time Distribution Look Ahead in Scheduler 1.2
- Integration and test with Scheduler
Support Development for Time Distribution Look Ahead in Scheduler 1.2
Planned Story Points = 59.0
Statement of Work
No description provided.
Issues
Number of Issues = 0
Support for previous release v1.1
Planned Story Points = 12.0
Statement of Work
No description provided.
Issues
Number of Issues = 0
Cadence Studies v1.2
Planned Story Points = 46.0
Statement of Work
No description provided.
Issues
Number of Issues = 0
Implement production tools v1.2
Planned Story Points = 55.0
Statement of Work
No description provided.
Issues
Number of Issues = 0
SOCS Release v1.3
Release Date: 2018-01-07
Statement of Work
- Support for previous release
- Evaluate and implement performance enhancements
Evaluate and implement performance enhancements
Planned Story Points = 76.0
Statement of Work
No description provided.
Issues
Number of Issues = 0
Support for previous release v1.2
Planned Story Points = 12.0
Statement of Work
No description provided.
Issues
Number of Issues = 0
Cadence Studies v1.3
Planned Story Points = 49.0
Statement of Work
No description provided.
Issues
Number of Issues = 0
Implement production tools v1.3
Planned Story Points = 59.0
Statement of Work
No description provided.
Issues
Number of Issues = 0
SOCS Release v1.4
Release Date: 2018-06-25
Statement of Work
- Support for previous release
- Implement warm start DB interface for Scheduler
- Implement image quality feedback simulator
- Implement degraded operational modes simulator
- Constrained limits and/or speeds for mount, rotator, dome, optics.
- Constrained availability of filters
- Integrate and test with Scheduler
- Test resuming partial surveys
- Test variable image quality feedback
- Test degraded modes
Implement warm start DB interface for Scheduler
Planned Story Points = 23.0
Statement of Work
No description provided.
Issues
Number of Issues = 0
Implement image quality feedback simulator
Planned Story Points = 23.0
Statement of Work
No description provided.
Issues
Number of Issues = 0
Implement degraded operational modes simulator
Planned Story Points = 23.0
Statement of Work
No description provided.
Issues
Number of Issues = 0
Integrate and test with Scheduler v1.4
Planned Story Points = 26.0
Statement of Work
No description provided.
Issues
Number of Issues = 0
Support for previous release v1.3
Planned Story Points = 12.0
Statement of Work
No description provided.
Issues
Number of Issues = 0
Cadence Studies v1.4
Planned Story Points = 60.0
Statement of Work
No description provided.
Issues
Number of Issues = 0
Implement production tools v1.4
Planned Story Points = 72.0
Statement of Work
No description provided.
Issues
Number of Issues = 0
SOCS Release v1.5
Release Date: 2018-11-17
Statement of Work
- Support for previous release
- Implement spatial distribution for weather simulator
- Integrate and test with Scheduler
- Test dithering in Scheduler
- Test spatial distribution for weather in a survey
Implement spatial distribution for weather simulator
Planned Story Points = 53.0
Statement of Work
No description provided.
Issues
Number of Issues = 0
Integrate and test with Scheduler v1.5
Planned Story Points = 29.0
Statement of Work
No description provided.
Issues
Number of Issues = 0
Support for previous release v1.4
Planned Story Points = 12.0
Statement of Work
No description provided.
Issues
Number of Issues = 0
Cadence Studies v1.5
Planned Story Points = 52.0
Statement of Work
No description provided.
Issues
Number of Issues = 0
Implement production tools v1.5
Planned Story Points = 62.0
Statement of Work
No description provided.
Issues
Number of Issues = 0
SOCS Release v2.0
Release Date: 2019-04-12
Statement of Work
- Support for previous release
- Support Scheduler Implementation for publication of future targets schedule
- Integrate and test with Scheduler
Support Scheduler Implementation for publication of future targets schedule
Planned Story Points = 70.0
Statement of Work
No description provided.
Issues
Number of Issues = 0
Integrate and test with Scheduler v2.0
Planned Story Points = 12.0
Statement of Work
No description provided.
Issues
Number of Issues = 0
Support for previous release v1.5
Planned Story Points = 12.0
Statement of Work
No description provided.
Issues
Number of Issues = 0
Cadence Studies v2.0
Planned Story Points = 52.0
Statement of Work
No description provided.
Issues
Number of Issues = 0
Implement production tools v2.0
Planned Story Points = 62.0
Statement of Work
No description provided.
Issues
Number of Issues = 0
SOCS Release v2.1
Release Date: 2019-08-17
Statement of Work
- Support for previous release
- Implement weather forecast
- Integrate and test with Scheduler
Implement weather forecast
Planned Story Points = 47.0
Statement of Work
No description provided.
Issues
Number of Issues = 0
Integrate and test with Scheduler v2.1
Planned Story Points = 24.0
Statement of Work
No description provided.
Issues
Number of Issues = 0
Support for previous release v2.0
Planned Story Points = 12.0
Statement of Work
No description provided.
Issues
Number of Issues = 0
Cadence Studies v2.1
Planned Story Points = 46.0
Statement of Work
No description provided.
Issues
Number of Issues = 0
Implement production tools v2.1
Planned Story Points = 55.0
Statement of Work
No description provided.
Issues
Number of Issues = 0
SOCS Release v2.2
Release Date: 2020-01-10
Statement of Work
- Support for previous release
- Support Scheduler implementation of generic interface for optimization algorithms
- Support Schedule Incorporation community provided optimizations
Support Scheduler implementation of generic interface for optimization algorithms
Planned Story Points = 35.0
Statement of Work
No description provided.
Issues
Number of Issues = 0
Support Scheduler incorporation of community provided optimizations
Planned Story Points = 47.0
Statement of Work
No description provided.
Issues
Number of Issues = 0
Cadence Studies v2.2
Planned Story Points = 52.0
Statement of Work
No description provided.
Issues
Number of Issues = 0
Implement production tools v2.2
Planned Story Points = 62.0
Statement of Work
No description provided.
Issues
Number of Issues = 0