Location
Zoom link available on Slack channel.
(Back to the DMCCB page)
Time
From 9.00 to 09.30 PT, Wednesdays.
Attendees: Wil O'Mullane Tim Jenness Yusra AlSayyad Jim Bosch Steve Pietrowicz Matthias Wittgen
Regrets: KT
DMCCB Meeting Goals
- See DMCCB responsibilities listed in LDM-294 section 7.4
DMCCB Additional Resources
Discussion Items
Item | Description | CCB Notes |
---|
Flagged RFCs (To be approved by the DMCCB) | -
RFC-771
-
Getting issue details...
STATUS
-
RFC-863
-
Getting issue details...
STATUS
-
RFC-889
-
Getting issue details...
STATUS
-
RFC-891
-
Getting issue details...
STATUS
|
889 -- wil to comment and recommend 891 needs status wait a week |
Board Recommended RFCs | -
RFC-888
-
Getting issue details...
STATUS
-
RFC-828
-
Getting issue details...
STATUS
-
RFC-892
-
Getting issue details...
STATUS
|
|
Proposed RFCs (to review, do not require DMCCB approval) | -
RFC-880
-
Getting issue details...
STATUS
-
RFC-884
-
Getting issue details...
STATUS
|
|
Adopted RFCs without Triggering issues (to create implementing DM issues) | | |
Open LCRs | -
RFC-876
-
Getting issue details...
STATUS
-
RFC-855
-
Getting issue details...
STATUS
| witing for victor to push button |
Adopted RFCs with all triggered work COMPLETED (to set status as 'IMPLEMENTED') | -
RFC-243
-
Getting issue details...
STATUS
|
|
RFCs adopted since the last DMCCB (to review, no action required) | -
RFC-867
-
Getting issue details...
STATUS
| |
RFCs implemented (or withdrawn) since the last DMCCB (to review, no action required) | -
RFC-883
-
Getting issue details...
STATUS
-
RFC-829
-
Getting issue details...
STATUS
-
RFC-763
-
Getting issue details...
STATUS
| |
|
|
|
Releases - Planned
- Changes to the release schedule
| - Next planned Releases 23.0.3 and 24.0.0 and 25.0.0
| - Report last week on Slack suggests that it is now impossible to build 23.0.2 because the associated rubin-env is not compatible.
- Yusra has a weekly - could start work on 25 but 24 is not out
- Matthias says only paperwork for 24 - characterization and release note - Yusra would release without chareterization report. Jim - RC2 run is more useful it does not tell us something useful. The release candidate has been run on 100 sqd of HSC.
- Chareterization report on 24.1 (need piff backorts) - Jeff
- Yusra - new features page
- Tim the middleware text
- Matthias the rest
- 24.0 priority over 23.03(needs env fix)
- dm-31972 - Jim to look
- 23.03 may just build - Colin did some SDM backport fixes (to confirm )- still need some legacy repo permission fixes (Matthias can do it - will talk to Tim)
- Jim ask s which is the last version with gen2 convert ? - All gen2 went on weekly 34 - v24 is the last with gen2.
- Who does Release 25 ?
- Yusra offers to do it
- Matthias will do it - notes it needs to be faster
- 25 is needed for ah LDM-503 milestone level 2 so need the reports etc ..
- 2 week test runnign on it now.
- probably weekly 48 - or does it need to be confirmed .
- Yusra says we could already tag an RC1.
- Matthias - could we have a SLACK group for release - Suggest adding Jeff to dm-ccb . Wil O'Mullane add Jeff to DM-CCB
|
Monitor Jira issues status: - the most forgotten 10 DM issues
- (resolution = Unresolved ORDER by updated asc)
| -
DM-2968
-
Getting issue details...
STATUS
-
DM-2872
-
Getting issue details...
STATUS
-
DM-1867
-
Getting issue details...
STATUS
-
DM-2476
-
Getting issue details...
STATUS
-
DM-2969
-
Getting issue details...
STATUS
-
DM-2904
-
Getting issue details...
STATUS
-
DM-18558
-
Getting issue details...
STATUS
-
DM-16929
-
Getting issue details...
STATUS
-
DM-18594
-
Getting issue details...
STATUS
-
DM-18613
-
Getting issue details...
STATUS
Unresolved issues: 4214 (we are now encountering old T&S tickets) | |
Open Actions | |
|
AOB | |
|
Next DM-CCB | 2022-12-07 |
|
Pending Flagged RFCs
Pending Proposed RFCs
Oldest issues
Meeting outcome
Pending DMCCB Actions
Task report
Looking good, no incomplete tasks.