Attendees

Discussion Items

ItemWhoNotes
Project updates
  • ComCam in Base Data Center - All Reil Photos
  • Jeff Barr - 5+Brian separately going to summit tomorrow check covers etc. Brian getting some ComCam kit from mountain (crane, nitrogen, electronics..) . Supposed to be no work on the recinto....
  • Parts of Santiago locked down - may spread further. Tracking obligations for travel/paperwork.
  • Discussion of any guidance from NSF/DOE on maintaining the staff/project. Both agencies have said not to foresee cuts - we are not in a financial crunch right now. Get any baseline work we can do done. 
  •  Chris Montgomery has done a lot with Litmus and LinkedIn Learning.
    • Includes multi-lingual courses.
    • Cybersecurity with Cristian Silva.
    • LinkedIn Learning added  3 new sets related to remote working.
  • Encouraging managers to engage with their groups to keep them engaged and motivated: morning checkins, BlueJeans coffee breaks, etc.
    • SIT-COM - weekly standup Tuesday
    • T&S - 
      • various - Chile still reacting to shutdown. 20 elec/mech techs all hands on - stopped morning meeting (perhpas should not have done)
      • Tucson weekly meeting - Doug keeping them engaged.
      • Cam meetings etc and contractor meetings continue
      • TSSW double down on standup - every day
    • COMs
      • daily chats and goal setting
    • EPO
      • standups mon,wed,fri
      • EPO Tea 10:30
      • co-work once a week
    • DM
      • Pipelines now combined UW/Princeton “brown bag”. Happy hour 18:30 Eastern Friday
      • SQuaRE mentioned longer Standups.
      • Slack ..
      • Universities also doing things.
    • Camera
      • Working as normal.
      • Slack channel.
  • Next project all hands meeting... not yet set, but discussing running one every other week.
CCB
  • Next DM-CCB 2020-04-01.
Ops Director's Review
  • Thanks, everybody, for your contributions!
  • Review outcome was positive.
  • Major recommendations for Data Production:
    • Concern about the location of the Data Facility.
    • Suggestion that there should be a technical “decision-making body” within the DP organization.
    • Be aware of technical risk/required effort involved in in-kind contributions.
  • Next up... Joint Agency Review.
    • Materials due on Friday of this week.
    • Review runs April 14–16.

Test Plans due in the next 45 days

Key Summary T Created Updated Due Assignee Reporter P Status Resolution
Loading...
Refresh

Milestones due in the next 45 days

Key Summary T Created Updated Due Assignee Reporter P Status Resolution
Loading...
Refresh

Any other business
  • Robert Gruendl is product owner for Prompt Services
    • This is expected to cover everything in the Prompt Base and Prompt NCSA enclaves, but not the scientific payloads that they exceute.
    • Not clear if it's supposed to cover e.g. alert distribution.
  • We believe that networking for LATISS is adequate to support an Ops Rehearsal (and general commissioning usage).
  • No Cassandra updates, as the DAX team is prioritizing middleware (at DMLT request).
  • Leanne Guy , Robert Gruendl , Kian-Tat Lim — clarify exactly of what Robert is product owner.   
  • Wil O'Mullane — Ensure that operations-era maintenance of packaging and distribution is captured in the Ops WBS (pretty sure that at the moment, it is mentioned, but the only associated resources are from IN2P3; not clear if that's adequate).   
DMLT travel & availability this week
  • Monday April 6 security summit 8–10 PT (so should be done before DMLT).
    • Contents, participants, etc of this meeting currently undefined as far as DM is aware — Wil O'Mullane will call on folks as & when required.

RFCs

Overdue

Key Summary Reporter Assignee Created planned end
Loading...
Refresh

Due this week

Key Summary Reporter Assignee Created planned end
Loading...
Refresh

Action Items

Confluence Quick Tasks

DescriptionDue dateAssigneeTask appears on
  • Frossie Economou Will recommend additional Level 3 milestones for implementation beyond just the DAX-9 Butler provenance milestone.   
15 Mar 2022Frossie EconomouDM Leadership Team Virtual Face-to-Face Meeting, 2022-02-15 to 17
  • Kian-Tat Lim Convene a meeting with Colin, Tim, Robert, Yusra to resolve graph generation with per-dataset quantities (likely based on Consolidated DB work).  
18 Mar 2022Kian-Tat LimDM Leadership Team Virtual Face-to-Face Meeting, 2022-02-15 to 17
  • Frossie Economou Write an initial draft in the Dev Guide for what "best effort" support means  
17 Nov 2023Frossie EconomouDM Leadership Team Virtual Face-to-Face Meeting - 2023-Oct-24
  • Convene a group to redo the T-12 month DRP diagram and define scope expectations Yusra AlSayyad 
30 Nov 2023Yusra AlSayyadDM Leadership Team Virtual Face-to-Face Meeting - 2023-Oct-24
11 Dec 2023Gregory Dubois-FelsmannDM Leadership Team Virtual Face-to-Face Meeting - 2023-Oct-24

DMLT-relevant Jira Tickets

Key Summary Reporter Assignee Created Due
Loading...
Refresh