Location

Browser

Room System

Phone Dial-in

https://bluejeans.com/293724745/

  1. Dial: 199.48.152.152 or bjn.vc
  2. Enter Meeting ID: 293724745 -or- use the pairing code

Dial-in numbers:

  • +1 408 740 7256
  • +1 888 240 2560 (US Toll Free)
  • +1 408 317 9253 (Alternate Number)

Meeting ID: 293724745

Time

10:15am PT

Attendees

Regrets

Discussion Items

ItemWhoNotes
Project updates
  • OIR lab council this week in Tucson - Ed Ajhar in town. 
  • Status slides for AMCL .. 
  • Naming  - email exchanges continue on terminology  
    • 20 minute naming discussion (all hands) next week Tuesday -  followed by lunch (Tucson)
    • message will be sent today
    • slides from AAS in docushare link will be sent. Templates to come in two days. (perhaps bundled)
  • ComCam quad box arrived with 3 SLAC people who were not registered - we need to register visits in Jira.
    • Making a TR does this for us automatically - so mainly for others not in our TR system
  • TMA test plan review in Spain next week (Chuck/Sandrine)
  • talk about safety procedures and hazard analysis and mitigation
  • LCR-2045 (commissioning de scope) and DM hardware (LCR-2148) need to go the NSF board this week.
  • Lots of people in Chile for dome, VA coating chamber  (9) and TMA (13)
    • could be last VA trip (final interface testing), though may support M1M3 coating later.
  • Camera back flange flatness non conformance - requirement was arbitrary but needs some analysis from Doug.
  • EPO have new tram member in Chile - moving to Tucson (web designer)
  • Bulk head plate connector also problematic.
DMLT vF2F
  • The next DMLT face-to-face meeting will be virtual (ie, on BlueJeans), and will take place from 24 to 27 February (ie in six weeks).
  • Details are on this Confluence page.
  • Please add your suggested agenda items to that page by 10 February.
Crosstalk

LCR 1923 is approved. So we need to look at the image extraction and transfer.Mentioned to Kian-Tat Lim before the break.

  • Should we consider only one read out shared with camera ?
  • The image transferred for Alerts as the only transfer?
    • what about copy at La Serena
  • Kian-Tat Lim to report on the impact of LCR-1923 (De-Scope Camera DAQ Crosstalk Correction) on DM at the February DMLT vF2F.  
CCBOld tickets  - as sent in email this AM - John and Frossie.
Level 2 Milestones

Test Plans due in the next 45 days

Key Summary T Created Updated Due Assignee Reporter P Status Resolution
Loading...
Refresh

Milestones due in the next 45 days

Key Summary T Created Updated Due Assignee Reporter P Status Resolution
Loading...
Refresh

There was a bunch of discussion about whether the reviewer of the test report has to be able to replicate the test results, or if they can simply accept the documentation of a single test execution.

  • We agreed that a single successful execution is adequate to capture a milestone.
  • There was some discussion about putting tests in CI, but this seems inconclusive from a policy standpoint.
Any other business
  • Jeff Kantor reports readiness for LATISS.
  • Jeff Kantor met with Cristián Silva to go over Jira questions.
  • Michelle Butler reports commissioning cluster going to Chile in March.
  • Wil O'Mullane  reports that LDF relocation was discussed at the quarterly agencies meeting last week. No conclusions yet; expect news in the next week or two.
DMLT travel & availability this week
No meeting next week due to Marin Luther King Jr Day

RFCs

Overdue

Key Summary Reporter Assignee Created planned end
Loading...
Refresh

Due this week

Key Summary Reporter Assignee Created planned end
Loading...
Refresh

Action Items

Confluence Quick Tasks

DescriptionDue dateAssigneeTask appears on
  • Kian-Tat Lim  & Michelle Butler  — propose a design and schedule for deploying a rapid processing system at the LDF.  
29 May 2020Kian-Tat LimDMLT Meeting - 2020-03-02
  • Michelle Butler  & Gregory Dubois-Felsmann  — identify existing requirements, or suggest new requirements, for a user-facing ”bulk-download“ service (but not under that name).  
05 Jun 2020Michelle ButlerDM Leadership Team Virtual Face-to-Face Meeting, 2020-02-25 to 27
  • Wil O'Mullane — make sure a L2 milestone for the Science Platform exists in P6.  
15 Jun 2020Wil O'MullaneDMLT Meeting - 2020-06-08
  • DMTN-148 is almost there suggest 2 weeks review by DMLT.  
15 Jun 2020 DM Leadership Team Virtual Face-to-Face Meeting, 2020-05-12/14
29 Jun 2020John SwinbankDMLT Meeting - 2020-06-22
  • Gregory Dubois-Felsmann  — update the Science Platform design documentation to reflect that data access services should be tested with PyVO.  
01 Jul 2020Gregory Dubois-FelsmannDM Leadership Team Virtual Face-to-Face Meeting, 2020-05-12/14
  • Colin Slater — Augment LDM-153 to provide a description of the semantics of NULL, NaN, inf, and other database vocabulary.  
06 Jul 2020Colin SlaterDM Leadership Team Virtual Face-to-Face Meeting, 2020-05-12/14
06 Jul 2020Wil O'MullaneDM Leadership Team Virtual Face-to-Face Meeting, 2020-05-12/14
  • Fritz Mueller — engage with the LDF and, as necessary, AP team to best understand the data structures required for the APDB.  
06 Jul 2020Fritz MuellerDM Leadership Team Virtual Face-to-Face Meeting, 2020-05-12/14
  • Fritz Mueller — Draft an technote describing operational procedures for database ingest.  
03 Aug 2020Fritz MuellerDM Leadership Team Virtual Face-to-Face Meeting, 2020-05-12/14