we are on NSF watch list - monthly meetings. Victor keeping Ed informed. Monthly financial data tends to be 5 to 6 weeks behind reality (just closing Oct). Ed Ajhar will be given access to Thursday status page
Data summit early Feb. Not clear what this is about yet — need to agree scope. Finalize construction plans and where it fits with operations and tidy up things like network security.
Meeting attendance (large meetings)
AAS — not too restrictive — not so many people want to go.
3 comms , 2 DM , 1 EPO, 1 Project office, 1 System Eng
LSST@Europe 4 - Many people invited 5 DM people would like to go.
We need to supply Zeljko a list of DM people who will be going within 2 days; if you want to go, your name must appear on the confluence page.
People interested in giving a remote talk should also add their name to the Confluence page.
should make progress on construction - Victor is supportive. This should not be to bring in more OPS contributions anymore.
Amanda/Lynne would do remote presentations.
Only Zeljko going from Project Office ..
Bob and Phil going on OPS - perhaps fund more if we can justify as OPS
SPIE -
T&S 4 people - 8 papers
Project Office - 1
DM
AAS
Potential protestors at the door.
There will be press releases — frustration with NSF on details.
Open house
LSSTC to be worked into agenda
How to pin down dates like first light - P6 baseline dates - forecast dates - table of monthly milestones uses this terminology. Some fact sheets are contradictory.
Vincent looking for end date of project- LCR-2045. Victor will figure this out
All DMLT: Add your name ot the Conferences and Workshops with DM Involvement (including indication as to whether you would give a remote presentation) page if you want to go to to LSST@Europe4, or if you want to give a remote talk.
Leanne Guy & Jeffrey Carlin will be running an “acceptance test” campaign testing the released science pipelines against all defined verification tests.
December / January timescale.
HSC RC2 has been reprocessed with w_2019_46 (which is the basis of the 19.0.0 release) already (
DM-22223
-
Getting issue details...STATUS
); should be a good basis for testing.
Kian-Tat Lim Convene a meeting with Colin, Tim, Robert, Yusra to resolve graph generation with per-dataset quantities (likely based on Consolidated DB work).