Time

10:15am PT

Attendees

Regrets

Discussion Items

ItemWhoNotes
Project updates
  • Key milestones advertised at the JSR include the hand over from dome to TMA priority on 15 October.
    • Schedule for this looks shaky.
    • NSF director will be on site 18 October.
    • Victor/Steve/Vincent will be in Washington next week to set expectations in advance of that meeting.
    • May be some schedule impacts on DM — not clear what yet — Victor threatening to ping John Swinbank for input this week; will call on the rest of the DMLT as necessary.
  • Publications.
    • A list of manuscripts that the project will be producing over the next couple of years as the canonical citable material on LSST was circulated by Zeljko Ivezic over the weekend.
    • John Swinbank saw a copy just before this meeting; haven't yet had time to digest.
    • Several people from DM are listed as primary points of contact (which doesn't necessarily mean lead author)
    • Please take the time now to look at what you are being signed up for and work with your T/CAM to understand any impact on your other work.
  • Revised commissioning schedule forthcoming.
  • Lots of interactions with vendors on scheduling; project trying hard to get on top of this before agency meeting referred to above.
  • Filter changer review last week.
    • Several issues arising from that will need to be addressed.
    • A “laundry list” of 28 items.
    • Vincent Riot's recommendation is that shipping from France can go ahead without waiting for all items to be addressed.
PST updates
  • Most relevant discussion about papers; Z has nothing to add to the above.
  • Decision has been made on naming: “LSST will not change” in the codebase, etc, but not yet public what will happen beyond that.
    • Announcement at AAS meeting in January.
  • Robert Lupton is “grovelling down” into the T&S software, including SAL.
    • Will take some effort away from DM.
Data Facility — DOE investigationJohn Swinbank
  • Some initial thoughts from DM on DMTN-134; feedback welcome.
  • Expecting Bob Blum to drive the process this week — more news when we have it.
DMLT F2F meeting
  • The next face-to-face meeting will take place in four weeks.
  • Please make sure your TR is submitted & your accommodation booked at the Creekside Inn (use that link).
  • Please add topic suggestions/requests to the Confluence page this week.
Risk Review
  • Review board meeting is tomorrow.
  • By this stage, all risks should have been reviewed. Have they been?
SPIE, June 2020, JapanJohn Swinbank
  • The PMO will be coordinating attendance following the procedure/forms at SPIE Conference in Yokohama-Japan, Meeting: 14 June – 19 June 2020.
  • Following last week's discussion, I think we know who is likely to go from this meeting from DM, but please jump through the required hoops anyway.
  • Also please make sure your team know about the process.
Level 2 Milestones

Test Plans due in the next 45 days

Key Summary T Created Updated Due Assignee Reporter P Status Resolution
Loading...
Refresh

Milestones due in the next 45 days

Key Summary T Created Updated Due Assignee Reporter P Status Resolution
Loading...
Refresh

Any Other Business
DMLT Travel & Availability this week
Review open action items

RFCs

Overdue

Key Summary Reporter Assignee Created planned end
Loading...
Refresh

Due this week

Key Summary Reporter Assignee Created planned end
Loading...
Refresh

Action Items

Confluence Quick Tasks

DescriptionDue dateAssigneeTask appears on
  • Frossie Economou Will recommend additional Level 3 milestones for implementation beyond just the DAX-9 Butler provenance milestone.   
15 Mar 2022Frossie EconomouDM Leadership Team Virtual Face-to-Face Meeting, 2022-02-15 to 17
  • Kian-Tat Lim Convene a meeting with Colin, Tim, Robert, Yusra to resolve graph generation with per-dataset quantities (likely based on Consolidated DB work).  
18 Mar 2022Kian-Tat LimDM Leadership Team Virtual Face-to-Face Meeting, 2022-02-15 to 17
  • Frossie Economou Write an initial draft in the Dev Guide for what "best effort" support means  
17 Nov 2023Frossie EconomouDM Leadership Team Virtual Face-to-Face Meeting - 2023-Oct-24
  • Convene a group to redo the T-12 month DRP diagram and define scope expectations Yusra AlSayyad 
30 Nov 2023Yusra AlSayyadDM Leadership Team Virtual Face-to-Face Meeting - 2023-Oct-24
11 Dec 2023Gregory Dubois-FelsmannDM Leadership Team Virtual Face-to-Face Meeting - 2023-Oct-24
02 May 2024Frossie EconomouDMLT Meeting - 2024-04-22
22 May 2024 DMLT Meeting - 2024-04-22
  • Richard Dubois USDF part in data facilities for PSTN-017 and distrib processing ? 
22 May 2024Richard DuboisDMLT Meeting - 2024-04-22
22 May 2024Fabio HernandezDMLT Meeting - 2024-04-22
  • Tim Jenness - section on middleware for PSTN-017  
22 May 2024Tim JennessDMLT Meeting - 2024-04-22
  • Cristián Silva - section on summit/data acquisition  for PSTN-017  
22 May 2024Cristián SilvaDMLT Meeting - 2024-04-22

DMLT-relevant Jira Tickets

Key Summary Reporter Assignee Created Due
Loading...
Refresh