  • Planning for the Cadence Workshop Dry Run Jun 9,10 – Zeljko / Steve
  • Updates on Tier 1 runs - Kem
  • JIRA  - updates on Sprint 9

Discussion 

  1. The power outage has taken down the Atlassian products but Iain and Mario are working on it
  2. Dry Run - Monday afternoon will be MAF presentations as in the All Hands meeting; Tues will be plenary talks; Wed is the PST in Seattle
  3. Conf parameters - Francisco will write a response to Lynnes email about the new conf parameter usage and we can include this in our documentation
  4. We are discussing whether and when to include MAF documentation in Sphinx
  5. MAF outcomes:
    1. documentation plan
    2. plan of activity to Aug 2014
    3. plan for MAF development moving forward