This page details the SOCS workplan with planned and actual storypoints.
Updated: 2017-08-31 15:19

SOCS Release v1.

...

1 (SIM-

...

1287)

Release Date: 20162017-1007-2731
Status = DoneIn Progress

Statement of Work

  • Support for previous release
  • Support Development for Area Distribution Look Ahead in Scheduler 1.1
  • Implement non deterministic weather simulator
  • Implement non deterministic downtime simulator
  • Integrate and test
  • Refactor and integrate Environment Model
  • Simulate weather telemetry, clouds and seeing
  • Incorporate filter swaps during new moon
  • Incorporate downtime simulator
  • Implement Scheduler configuration via commands
  • Integrate with Scheduler
    • Test with complete surveysurvey with Area Distribution proposals and Look Ahead
    • Test repeatabilityspeed performance
    • Test execution speed

...

    • repeatability

Support for previous release v1.0 (SIM-

...

1945)

Planned Story Points = 10.0
Status = DoneIn Progress

Statement of Work

  • Create module for downtime information
  • Create classes for handling the downtime information
  • Handle configuration overriding of the downtime information
  • Make the simulator handle downtime
  • Handle issues arising from testing the v1.0 release
Number of Issues (Stories) =

...

10

Key

Description

Status

Story Points

SIM-2106

Use downtime in simulator

Done

2420

Support work for August

In Progress

15.0

SIM-20172409

Initial downtime Support work for July

Done

51.0

Integrate and test with Scheduler v1.0 (SIM-1344)

Planned Story Points = 25.0
Status = Done

Statement of Work

  • Perform "continous" integration testing between SOCS and Scheduler
  • Update ICD to reflect any changes in topic information
Number of Issues (Stories) = 5

Key

Description

Status

Story Points

SIM-2130

SOCS/Scheduler testing

Done

5.0

SIM-2105

SOCS/Scheduler testing

Done

5.0

SIM-2074

SOCS/Scheduler testing

Done

5.0

SIM-2065

SOCS/Scheduler testing

Done

5.0

SIM-2016

SOCS/Scheduler testing

Done

5.0

Cadence studies in cycle v1.0 (SIM-1389)

SIM-2374

Support work for June 2017

Done

2.0

SIM-2343

Support work for May

Done

2.0

SIM-2316

Add parameters for restarting sequences

Done

0.5

SIM-2311

Ensure cloud and seeing models have concept of time of year

Done

0.2

SIM-2310

Support work for March

Done

3.0

SIM-2308

Fix session tracking

Done

0.1

SIM-2299

Change sim start date to 10/01/2022

Done

0.1

SIM-2298

Correct time window configuration for DeepDrillingCosmology1

Done

0.1

Support Development for Area Distribution Look Ahead in Scheduler 1.1 (SIM-1345)

Planned Story Points = 15.0
Status = Done

Statement of Work

  • Provide support to Scheduler developer
  • Provide configuration for Area Distribution Look Ahead
Number of Issues (Stories) = 0

Implement non-deterministic weather simulator (SIM-1346)

Planned Story Points = 10Planned Story Points = 42.0
Status = Done

Statement of Work No description provided.

  • Implement system to use generated weather distributions
  • Implement configuration for using non-deterministic system
Number of Issues (Stories) =

...

0

Integrate and test with Scheduler v1.1 (SIM-1347)

Planned Story Points = 25.0
Status = Done

Statement of Work

  • Perform routine integration work with the Scheduler
  • Update ICD as necessary
Number of Issues (Stories) = 2

Key

Description

Status

Story Points

SIM-2372

SOCS/Scheduler testing for June 2017

Done

5.0

SIM-2371

SOCS/Scheduler testing March-May 2017

Done

15.0

Implement non-deterministic downtime simulator (SIM-1348)

Planned Story Points = 15.0
Status = Done

Statement of Work

  • Create distribution for unscheduled downtime
  • Implement system to use non-deterministic unscheduled downtime
  • Implement configuration for system
Number of Issues (Stories) = 0

Cadence studies in cycle v1.1 (SIM-1392)

Planned Story Points = 95.0
Status = Done

Statement of Work
No description provided.

Number of Issues (Stories) = 33

Key

Description

Status

Story Points

SIM-2413

Attend Scheduler Development Coordination Meeting in Seattle July 11-13

Done

3.0

SIM-2412

Attend SOCS Workshop in Tucson July 5-7

Done

2.0

SIM-2411

Attend SOCS Workshop in Tucson July 5-7

Done

2.0

SIM-2410

Strategic planning meetings (weekly and as needed) July

Done

2.0

SIM-2406

V&V production - investigate variety of parameter settings for v4 and debug

Done

3.0

SIM-2405

Development and setup of processes and tools to create V&V runs

Done

4.0

SIM-2402

V&V - investigate variety of characteristics of v4 and debug

Done

4.0

SIM-2401

V&V - investigate variety of characteristics of v4 and debug

Done

3.0

SIM-2373

Support for V&V work with version 4 code

Done

5.0

SIM-2370

Strategic planning meetings (weekly and as needed) June

Done

2.0

SIM-2351

Rerun MAF on V&V runs and and analyze parameter impacts

Done

3.0

SIM-2350

Rerun MAF on V&V runs and and analyze parameter impacts

Done

3.0

SIM-2349

Review and update all default parameters for v4

Done

1.0

SIM-2348

Review and update all default parameters for v4

Done

1.0

SIM-2347

Strategic planning meetings (weekly and as needed) May

Done

1.0

SIM-2345

Support setup and running V&V runs, MAF and compiling results.

Done

3.0

SIM-2340

Support for V&V work with version 4 code

...

Key

...

Description

...

Status

...

Story Points

...

SIM-2132

...

Support cadence studies for oct (rolling, dd, tier 1, etc)

...

Done

...

3.0

...

SIM-2131

...

Evaluate impact of new filter change time and closed loop optics correction

...

Done

...

2.0

...

SIM-2115

...

advertise old rolling cadence and DD tests

...

Done

...

1.0

...

SIM-2101

...

Support cadence study effort (including new lsst.org pages)

...

Done

...

3.0

...

SIM-2100

...

Design v1.0 verification & validation planned simulations

...

Done

...

2.0

...

SIM-2099

...

Review lsst.org webpages for Simulations (update esp. "LSST Science Pipelines"

...

Done

...

1.5

...

SIM-2098

...

New Reference Run - create new webpage on lsst.org, write and release announcements to public

...

Done

...

1.5

...

SIM-2083

...

Attend LSST2016

...

Done

...

2.5

...

SIM-2082

...

Attend LSST2016

...

Done

...

5.0

...

SIM-2081

...

Execute variation on minion_1016 with new closed loop values & filter change time

...

Won't Fix

...

2.0

...

SIM-2072

...

Generate & display MAF analysis of weather runs with correct cloud table

...

Done

...

1.0

...

SIM-2071

...

Support creation of LCR, materials and collections for new Reference Run

...

Done

...

3.0

...

SIM-2063

...

Identify strategy for validation and verification of v1.0

...

Done

...

1.0

...

SIM-2062

...

Identify strategy for validation and verification of v1.0

...

Done

...

1.0

...

SIM-2028

...

Support preparation of CCB documents for new Reference Run

...

Done

...

4.5

...

SIM-2018

...

Resurrect and redesign isolated rolling cadence regions for config files

...

Done

...

3.0

Production tools in cycle v1.0 (SIM-1390)

Planned Story Points = 42.0
Status = Done

Statement of Work
No description provided.

Number of Issues (Stories) = 10

Key

Description

Status

Story Points

SIM-2119

Attend Software Carpentry workshop

Done

2.0

SIM-2103

August monthly reporting

Done

0.5

SIM-2102

July monthly reporting

Done

0.5

SIM-2073

Upgrades for ops2 - verify current data, archived data, install stack

Done

2.0

SIM-2035

Upgrades to ops2 - OS, disk space, sims_operations, sims_maf

Done

2.0

SIM-2034

Monthly Reporting for May

Done

1.0

SIM-2027

Recreate cloud tables and re-run simulations and modifySchema.sh

Done

5.0

SIM-2021

prepare talk from SPIE paper for SPIE meeting

Won't Fix

2328

Create github repository for trackingDbs, document all ports

Done

13.0

SIM-20192322

Strategic planning meetings (weekly and as needed)Tutorial for setting up and using configuration files in opsim3_config

Done

21.0

SIM-1973

Run Log - upgrade ops2 disks and software to enable running latest MAF (include EUPS) and simulator; php v. visual basic investigation for webserver.

Done

3.0

Implement Environmental Model (SIM-1941)

Planned Story Points = 15.0
Status = Done

Statement of Work

  • Convert old cloud table into SQLite DB file
  • Convert old seeing table into SQLite DB file
  • Create module for environmental information generation
  • Create classes for reading environmental databases
  • Create topics for passing environmental information
  • Add configuration and documentation for overriding the environmental information
Number of Issues (Stories) = 2

Key

Description

Status

Story Points

SIM-2133

Integrate weather information into system

Done

10.0

SIM-2080

Initial work on weather information

Done

5.0

More Observatory Model Enhancements (SIM-1942)

Planned Story Points = 15.0
Status = Done

Statement of Work

  • Implement filter swapping at new/full moon
  • Implement filter changes constraints
  • Implement initial variational model
Number of Issues (Stories) = 1

Key

Description

Status

Story Points

SIM-2107

Handle filter swaps in SOCS

Done

10.0

Infrastructure Enhancements (SIM-1944)

Planned Story Points = 20.0
Status = Done

Statement of Work

  • See if EUPS can be a viable deployment
  • Handle Conda installation if EUPS works
  • Create a Docker image
  • Ensure current configurations received by Scheduler
  • Implement any necessary Scheduler specific configuration
Number of Issues (Stories) = 4

Key

Description

Status

Story Points

SIM-2129

Infrastructure work for October

Done

5.0

SIM-2104

Infrastructure work for September

Done

5.0

SIM-2075

Infrastructure work for August

Done

5.0

SIM-2066

Infrastructure work for July

Done

5.0

SOCS Extended v1.0 Development (SIM-2167)

Planned Story Points = 64.0
Status = Done

Statement of Work
No description provided.

Number of Issues (Stories) = 16

Key

Description

Status

Story Points

SIM-2256

User interface work for February

Done

3.0

SIM-2255

Scheduler optimization work for February

Done

5.0

SIM-2254

SOCS/Scheduler testing for February

Done

4.0

SIM-2253

Infrastructure work for February

Done

4.0

SIM-2243

SOCS/Scheduler testing for January

Done

4.0

SIM-2242

User interface work for January

Done

3.0

SIM-2241

Scheduler optimization work for January

Done

5.0

SIM-2240

Infrastructure work for January

Done

4.0

SIM-2228

User interface work for December

Done

3.0

SIM-2227

SOCS/Scheduler testing for December

Done

4.0

SIM-2226

Scheduler optimization work for December

Done

5.0

SIM-2225

Infrastructure work for December

Done

4.0

SIM-2203

User interface work for November

Done

3.0

SIM-2202

Scheduler optimization work for November

Done

5.0

SIM-2201

SOCS/Scheduler testing for November

Done

4.0

SIM-2200

Infrastructure work for November

Done

4.0

Cadence studies and validation - verification in v1.0.ext (SIM-2168)

Planned Story Points = 64.0
Status = Done

Statement of Work
No description provided.

Number of Issues (Stories) = 0

SOCS Release v1.1 (SIM-1287)

Release Date: 2017-07-31
Status = In Progress

Statement of Work

  • Support for previous release
  • Support Development for Area Distribution Look Ahead in Scheduler 1.1
  • Implement non deterministic weather simulator
  • Implement non deterministic downtime simulator
  • Integrate and test with Scheduler
    • Test survey with Area Distribution proposals and Look Ahead
    • Test speed performance
    • Test repeatability

Cadence studies in cycle v1.1 (SIM-1392)

Planned Story Points = 95.0
Status = In Progress

Statement of Work
No description provided.

Number of Issues (Stories) = 32

...

Key

...

Description

...

Status

...

Story Points

...

SIM-2351

...

Rerun MAF on V&V runs and and analyze parameter impacts

...

To Do

...

3.0

...

SIM-2350

...

Rerun MAF on V&V runs and and analyze parameter impacts

...

To Do

...

3.0

...

SIM-2349

...

Review and update all default parameters for v4

...

To Do

...

1.0

...

SIM-2348

...

Review and update all default parameters for v4

...

To Do

...

1.0

...

SIM-2347

...

Strategic planning meetings (weekly and as needed) May

...

To Do

...

1.0

...

SIM-2345

...

Support setup and running V&V runs, MAF and compiling results.

...

Done

...

3.0

...

SIM-2340

...

Support for V&V work with version 4 code

...

In Progress

...

5.0

...

SIM-2328

...

Create github repository for trackingDbs, document all ports

...

Done

...

1.0

...

SIM-2323

...

opsim4: Establish sky brightness limits for all filters in all baseline proposals

...

In Progress

...

2.0

...

SIM-2322

...

Strategic planning meetings (weekly and as needed)

...

Done

...

1.0

...

SIM-2321

...

Support V&V work with version 4 code

...

Done

...

5.0

...

SIM-2320

...

Add edit capability to new run log

...

Duplicate

...

3.0

...

SIM-2319

...

Publish opsim3 Tier 1 runs with newer MAFs on 8686

...

Done

...

0.5

...

SIM-2318

...

Add edit capability to alhena run log

...

In Progress

...

3.0

...

SIM-2309

...

Setup replacement db and interface for run log on alhena

...

Done

...

3.0

...

SIM-2294

...

V & V - define strategy for parameter optimization

...

Done

...

1.0

...

SIM-2293

...

V & V - itemize runs and priorities

...

Done

...

2.0

...

SIM-2289

...

Strategic planning meetings (weekly and as needed)

...

Done

...

1.0

...

SIM-2288

...

Attend JTM

...

Done

...

3.0

...

SIM-2287

...

Attend JTM

...

Done

...

3.0

...

SIM-2263

...

opsim4: Test limit on tuples requested per night (2, 3, 4) - field v. field/filter

...

In Progress

...

3.0

...

SIM-2215

...

Run the latest MAF (with filter stat corrections) on Tier 1 runs

...

Done

...

2.0

...

SIM-2213

...

Opsim3: Generate reuse parameter runs - run at 1, 5, 10 to see impact on filter change stats.

...

To Do

...

3.0

...

SIM-2114

...

Outline Francisco's visualization, real time analysis tool definition; include maf standard metrics list.

...

In Progress

...

2.0

...

SIM-2085

...

opsim4: Generate simulations with 3-4 minute return time for NEOs

...

To Do

...

3.0

...

SIM-2084

...

opsim4: Generate simulations with added Euclid area

...

In Progress

...

3.0

...

SIM-1975

...

Analyze and summarize results of weather study

...

To Do

...

2.0

...

SIM-1879

...

Write outline for opsim paper for publication

...

In Progress

...

1.0

...

SIM-1832

...

Develop method to cross compare or view results from weather runs

...

To Do

...

2.0

...

SIM-1624

...

Write document on deep drilling and filter change requirements

...

In Progress

...

1.0

...

SIM-1621

...

opsim3: Test rolling cadence with isolated userRegions and no overlap, and start/stop times

...

In Progress

...

5.0

...

SIM-1081

...

opsim3: Generate permutations of reference runs with various auxiliary proposals

...

In Progress

...

3.0

2321

Support V&V work with version 4 code

Done

5.0

SIM-2320

Add edit capability to new run log

Duplicate

3.0

SIM-2319

Publish opsim3 Tier 1 runs with newer MAFs on 8686

Done

0.5

SIM-2318

Add edit capability to alhena run log

Done

3.0

SIM-2309

Setup replacement db and interface for run log on alhena

Done

3.0

SIM-2294

V & V - define strategy for parameter optimization

Done

1.0

SIM-2293

V & V - itemize runs and priorities

Done

2.0

SIM-2289

Strategic planning meetings (weekly and as needed)

Done

1.0

SIM-2288

Attend JTM

Done

3.0

SIM-2287

Attend JTM

Done

3.0

SIM-2215

Run the latest MAF (with filter stat corrections) on Tier 1 runs

Done

2.0

SIM-2213

Opsim3: Generate reuse parameter runs - run at 1, 5, 10 to see impact on filter change stats.

Done

3.0

SIM-1975

Analyze and summarize results of weather study

Done

2.0

SIM-1832

Develop method to cross compare or view results from weather runs

Done

2.

Support for previous release v1.0 (SIM-1945)

Planned Story Points = 10.0
Status = In Progress

Statement of Work

  • Handle issues arising from testing the v1.0 release
Number of Issues (Stories) = 7

...

Key

...

Description

...

Status

...

Story Points

...

SIM-2343

...

Support work for May

...

In Progress

...

2.0

...

SIM-2316

...

Add parameters for restarting sequences

...

Done

...

0.5

...

SIM-2311

...

Ensure cloud and seeing models have concept of time of year

...

Done

...

0.2

...

SIM-2310

...

Support work for March

...

Done

...

3.0

...

SIM-2308

...

Fix session tracking

...

Done

...

0.1

...

SIM-2299

...

Change sim start date to 10/01/2022

...

Done

...

0.1

...

SIM-2298

...

Correct time window configuration for DeepDrillingCosmology1

...

Done

...

0.1

Support Development for Area Distribution Look Ahead in Scheduler 1.1 (SIM-1345)

Planned Story Points = 15.0
Status = To Do

Statement of Work

  • Provide support to Scheduler developer
  • Provide configuration for Area Distribution Look Ahead
Number of Issues (Stories) = 0

Implement non-deterministic weather simulator (SIM-1346)

Planned Story Points = 10.0
Status = To Do

Statement of Work

  • Implement system to use generated weather distributions
  • Implement configuration for using non-deterministic system
Number of Issues (Stories) = 0

Integrate and test with Scheduler v1.1 (SIM-1347)

Planned Story Points = 25.0
Status = To Do

Statement of Work

  • Perform routine integration work with the Scheduler
  • Update ICD as necessary
Number of Issues (Stories) = 0

Implement non-deterministic downtime simulator (SIM-1348)

Planned Story Points = 15.0
Status = To Do

Statement of Work

  • Create distribution for unscheduled downtime
  • Implement system to use non-deterministic unscheduled downtime
  • Implement configuration for system

...

0

Create Weather Distributions (SIM-1946)

Planned Story Points = 20.0
Status = To DoDone

Statement of Work

  • Create distributions for clouds and/or transparency
  • Create distributions for seeing
Number of Issues (Stories) = 0

SOCS Release v1.2 (SIM-1288)

Release Date: 2017-08-24
Status = To DoDone

Statement of Work

  • Support for previous release
  • Support Development for Time Distribution Look Ahead in Scheduler 1.2
  • Integration and test with Scheduler

...

Planned Story Points = 59.0
Status = To DoDone

Statement of Work
No description provided.

Number of Issues (Stories) = 0

Support for previous release v1.1 (SIM-1414)

Planned Story Points = 12.0
Status = To DoDone

Statement of Work
No description provided.

Number of Issues (Stories) = 0

Integrate and test with Scheduler v1.2 (SIM-1415)

Planned Story Points = 12.0
Status = To DoDone

Statement of Work
No description provided.

Number of Issues (Stories) = 0

Cadence Studies v1.2 (SIM-1416)

Planned Story Points = 83.0
Status = To DoDone

Statement of Work
No description provided.

Number of Issues (Stories) = 0

SOCS Release v1.3 (SIM-1289)

Release Date: None
Status = To DoDone

Statement of Work

  • Support for previous release
  • Evaluate and implement performance enhancements

...

Planned Story Points = 76.0
Status = To DoDone

Statement of Work
No description provided.

Number of Issues (Stories) = 0

Support for previous release v1.2 (SIM-1418)

Planned Story Points = 12.0
Status = To DoDone

Statement of Work
No description provided.

Number of Issues (Stories) = 0

Cadence Studies v1.3 (SIM-1419)

Planned Story Points = 88.0
Status = To DoDone

Statement of Work
No description provided.

Number of Issues (Stories) = 0

SOCS Release v1.4 (SIM-1290)

Release Date: None
Status = To DoDone

Statement of Work

  • Support for previous release
  • Implement warm start DB interface for Scheduler
  • Implement image quality feedback simulator
  • Implement degraded operational modes simulator
    • Constrained limits and/or speeds for mount, rotator, dome, optics.
    • Constrained availability of filters
  • Integrate and test with Scheduler
    • Test resuming partial surveys
    • Test variable image quality feedback
    • Test degraded modes

...

Planned Story Points = 23.0
Status = To DoDone

Statement of Work
No description provided.

Number of Issues (Stories) = 0

Implement image quality feedback simulator (SIM-1354)

Planned Story Points = 23.0
Status = To DoDone

Statement of Work
No description provided.

Number of Issues (Stories) = 0

Implement degraded operational modes simulator (SIM-1355)

Planned Story Points = 23.0
Status = To DoDone

Statement of Work
No description provided.

Number of Issues (Stories) = 0

Integrate and test with Scheduler v1.4 (SIM-1356)

Planned Story Points = 26.0
Status = To DoDone

Statement of Work
No description provided.

Number of Issues (Stories) = 0

Support for previous release v1.3 (SIM-1421)

Planned Story Points = 12.0
Status = To DoDone

Statement of Work
No description provided.

Number of Issues (Stories) = 0

Cadence Studies v1.4 (SIM-1422)

Planned Story Points = 107.0
Status = To DoDone

Statement of Work
No description provided.

Number of Issues (Stories) = 0

SOCS Release v1.5 (SIM-1291)

Release Date: None
Status = To DoDone

Statement of Work

  • Support for previous release
  • Implement spatial distribution for weather simulator
  • Integrate and test with Scheduler
    • Test dithering in Scheduler
    • Test spatial distribution for weather in a survey

...

Planned Story Points = 53.0
Status = To DoDone

Statement of Work
No description provided.

Number of Issues (Stories) = 0

Integrate and test with Scheduler v1.5 (SIM-1358)

Planned Story Points = 29.0
Status = To DoDone

Statement of Work
No description provided.

Number of Issues (Stories) = 0

Support for previous release v1.4 (SIM-1424)

Planned Story Points = 12.0
Status = To DoDone

Statement of Work
No description provided.

Number of Issues (Stories) = 0

Cadence Studies v1.5 (SIM-1425)

Planned Story Points = 94.0
Status = To DoDone

Statement of Work
No description provided.

Number of Issues (Stories) = 0

SOCS Release v2.0 (SIM-1292)

Release Date: None
Status = To DoDone

Statement of Work

  • Support for previous release
  • Support Scheduler Implementation for publication of future targets schedule
  • Integrate and test with Scheduler

...

Planned Story Points = 70.0
Status = To DoDone

Statement of Work
No description provided.

Number of Issues (Stories) = 0

Integrate and test with Scheduler v2.0 (SIM-1360)

Planned Story Points = 12.0
Status = To DoDone

Statement of Work
No description provided.

Number of Issues (Stories) = 0

Support for previous release v1.5 (SIM-1427)

Planned Story Points = 12.0
Status = To DoDone

Statement of Work
No description provided.

Number of Issues (Stories) = 0

Cadence Studies v2.0 (SIM-1428)

Planned Story Points = 94.0
Status = To DoDone

Statement of Work
No description provided.

Number of Issues (Stories) = 0

SOCS Release v2.1 (SIM-1293)

Release Date: None
Status = To DoDone

Statement of Work

  • Support for previous release
  • Implement weather forecast
  • Integrate and test with Scheduler

...

Planned Story Points = 47.0
Status = To DoDone

Statement of Work
No description provided.

Number of Issues (Stories) = 0

Integrate and test with Scheduler v2.1 (SIM-1362)

Planned Story Points = 24.0
Status = To DoDone

Statement of Work
No description provided.

Number of Issues (Stories) = 0

Support for previous release v2.0 (SIM-1430)

Planned Story Points = 12.0
Status = To DoDone

Statement of Work
No description provided.

Number of Issues (Stories) = 0

Cadence Studies v2.1 (SIM-1431)

Planned Story Points = 83.0
Status = To DoDone

Statement of Work
No description provided.

Number of Issues (Stories) = 0

SOCS Release v2.2 (SIM-1294)

Release Date: None
Status = To DoDone

Statement of Work

  • Support for previous release
  • Support Scheduler implementation of generic interface for optimization algorithms
  • Support Schedule Incorporation community provided optimizations

...

Planned Story Points = 35.0
Status = To DoDone

Statement of Work
No description provided.

Number of Issues (Stories) = 0

Support Scheduler incorporation of community provided optimizations (SIM-1364)

Planned Story Points = 47.0
Status = To DoDone

Statement of Work
No description provided.

Number of Issues (Stories) = 0

Support for previous release v2.1 (SIM-1433)

Planned Story Points = 12.0
Status = To DoDone

Statement of Work
No description provided.

Number of Issues (Stories) = 0

Cadence Studies v2.2 (SIM-1434)

Planned Story Points = 94.0
Status = To DoDone

Statement of Work
No description provided.

Number of Issues (Stories) = 0