WBS 02C.04.06 (Object Characterization)

EpicSP estimateLikely assignee(s)Note
DM-8531Bosch (10%)Rolling over from W15.
DM-190760MacArthur (50%), Price (50%)Porting from HSC and other deblender infrastructure
DM-1908?MacArthur (100%)LSST deblender development
DM-1768/6922Gee (70%), Bosch (30%)Rolled over stores from the W15 measurement framework reworking + some new work. DM-1768 contains low priority miscellanea and doesn't need to be scheduled this cycle, but DM-1769 should be.
DM-106930 (provisional)Gee (100%)Measurement unit tests. Depends on DM-1102 (SQuaRE).
DM-110896Gee (75%), Bosch (25%)Galaxy Fitting - Shear Precision Experiments. Needs support from GalSim folks (Krughoff?)
DM-1111?New C++ developer if availableGalaxy Fitting - Micro Optimization. Not essential for our development goals to address this epic in this cycle, but may be necessary to inform hardware choices. Check with Mario.
DM-111060BoschGalaxy Fitting - Sampling Algorithm Plugin
DM-110920BoschDesign MultiFit plugin framework. Rolled over from W15. Depends on updated Butler (or we stub in our own temporary Butler-alike hack, which would be less than ideal).
(not yet created)50GeeImplement MultiFit plugin framework.

Total SP allocations

NameAvailability SPsAllocated SPsNote
Bosch

66

58Scientist, leader, 0.5 8 time
Gee78970.5 time
Lupton36106 SPs per month
MacArthur12659 + Undefined (deblender)Scientist
Price2440

Scientist, 0.5 2 time

Swinbank8498Scientist, leader
Total414  
Info

Agreed with HSC to split Bosch/Price 80/20 through this cycle.

 

Dependencies on other groups

SQuaRE: DM-1102, required for our DM-1069.

UW: DM-85. Astrometric & photometric self-calibration (which specific issues do these block?).

Middleware/Butler: DM-1109, multifit, etc.

To Do

  •  Agree plan for DM-85 with UW group
  •  Agree plan for DM-1102 with SQuaRE
  •  Agree plan for astrometry/photometry pipelines with UW group
  •  Discuss shifting measurement epics to 02C.04.06 with Jeff/Kevin
  •  What work will be addressed by HSC during S15 that we can claim partial credit for?
  •  Determine status of wavefront estimation code & consider an epic to integrate that with DM stack (02C.04.03)
  •  Agree allocation of Price/Bosch with HSC
  •  Estimate SPs for epics remaining above
  •  Question for Jeff/Kevin: For epics which we have only started to address in W15, should we close them down and create new epics for S15, or just carry the same epic over?
  •  Discuss timescale on which DM-1111 is required to inform hardware choices.