Item | Who | Notes | ||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Notes | last time Frossie Economou | |||||||||||||||||||||||||||||||||||||||||
Project Updates |
| |||||||||||||||||||||||||||||||||||||||||
DEI | See #inclusion and https://www.lsst.org/about/dei Community link: https://community.lsst.org/c/eji/45 | |||||||||||||||||||||||||||||||||||||||||
Replan | Wil O'Mullane Cristián Silva Yusra AlSayyad Frossie Economou had a short meeting with Victor/Kevin Long last wednsday:
Our (construction) story should be something like: With the delay DM has to maintain and keep everything upto date, AuxTel is getting a lot more care than was originally planned, that and other things are burning down risks for DM as we transition to operations. Additionally COVID has introduced an 11% ineficiency original planning. Of course we are also supporting preoperations and the USDF spin up but that is a different story.
Discussion with Robert Lupton and others about how to represent the AuxTel work's causes and benefits - risk reduction? understanding that certain on-summit issues are more complex than expected? transfer of learning experience from (e.g.) ComCam work to AuxTel work because of the long period with only AuxTel available? | |||||||||||||||||||||||||||||||||||||||||
Level 2 Milestones | Gen3 milestones chased - does not exist - email to decide date and text .. (June?) It seems in the new plan (+1 yr) many milestones moved out possible incorrectly - test plans * Wil O'Mullane will review all of these and put them back together in the right order
Test Plans due in the next 45 days
Milestones due in the next 45 days
| |||||||||||||||||||||||||||||||||||||||||
Risk Review | Risk meeting March 30th 15:00 PT (Tim Jenness will attend)
Risk items needing review
Overdue risks (obligation date passed)
Risk mitigations due at the end of this month
Overdue risk mitigations
| |||||||||||||||||||||||||||||||||||||||||
DMLT Travel & Availability this week | WOM - Workshop on Wednesday Gregory Dubois-Felsmann on call for jury duty through
| |||||||||||||||||||||||||||||||||||||||||
Any Other Business |
| |||||||||||||||||||||||||||||||||||||||||
TCAM Standup | as needed | |||||||||||||||||||||||||||||||||||||||||
Action review |
|
...