Noteslast time Frossie Economou
Project Updates
  1. We are moving forward with Next All-Hand meeting on Thursday 8 April at 9:00 PDT. Victor will be working with Ranpal, Sandrine, and Steve, as well as many other on putting together the agenda and charts.
    1. Replan update will be a big part of this
  2. Project Schedule messaging: Schedule charts shared a couple week ago represent the current picture. Victor  has a slight update to clarify the schedule contingency and we will present to Project at all-hands meeting.
  3. Discussion of broad community message (Timing, terminology, coordination with Agencies and Ops)
    1. While we have early end of construction community understand start of operations better
    2. Ops has not changed message from Oct 2023 start. Need to agree message between construction and ops. This is now not earlier than Oct 2023.
  4. Camera Refrigeration controllers were ready to ship end of last week - another problem found over weekend, should be crated today, shipping tomorrow.
  5. No current shipping in progress so no impact from Suez blockage.
    1. Our best wishes to keeping the Panama canal operational, though!
DEI


See  #inclusion and https://www.lsst.org/about/dei

Community link: https://community.lsst.org/c/eji/45

Replan


Wil O'Mullane Cristián Silva Yusra AlSayyad Frossie Economou had a short meeting with Victor/Kevin Long last wednsday:

  • Result of the Change - telescope completion 15 months delay. Early completion 1 Aug 2023. (Originaly May 6 2022)

  • some DM l2 milestones need adjusting (wrong logic),

  • we may need to check ops ramps (i.e. P6 shows us at same level while we have more FTE on OPS).

Our (construction) story should be something like: With the delay DM has to maintain and keep everything upto date, AuxTel is getting a lot more care than was originally planned, that and other things are burning down risks for DM as we transition to operations. Additionally COVID has introduced an 11% ineficiency original planning. Of course we are also supporting preoperations and the USDF spin up but that is a different story. 

  • We will acknowledge IT as part of DM, Cristian will be TCAM for a new WBS line (as well as LHN).
    • within that we will acknowledge some shift of scope within DM WBS
    • (some) Unused hardware budget (thanks Michelle) will be used to fund it
      • LCR will be required
    • Cristián will join DMLT and be added to DM org chart

Discussion with Robert Lupton and others about how to represent the AuxTel work's causes and benefits - risk reduction?  understanding that certain on-summit issues are more complex than expected? transfer of learning experience from (e.g.) ComCam work to AuxTel work because of the long period with only AuxTel available?

Level 2 Milestones


Gen3 milestones chased - does not exist - email to decide date and text .. (June?)

It seems in the new plan (+1 yr) many milestones moved out possible incorrectly - test plans

Wil O'Mullane will review all of these and put them back together in the right order

Jira
serverJIRA
jqlQueryfilter=18307
serverId9da94fb6-5771-303d-a785-1b6c5ab0f2d2

Test Plans due in the next 45 days

Jira
serverJIRA
columnskey,summary,type,created,updated,due,assignee,reporter,priority,status,resolution
maximumIssues20
jqlQuerylabels = TESTPLAN and resolution = Unresolved and due <= 45d order by id asc
serverId9da94fb6-5771-303d-a785-1b6c5ab0f2d2

Milestones due in the next 45 days

Jira
serverJIRA
columnskey,summary,type,created,updated,due,assignee,reporter,priority,status,resolution
maximumIssues20
jqlQueryproject = DM and labels = L2Milestone and team not in ("Telescope and Site") and resolution = Unresolved and due <= 45d order by id asc
serverId9da94fb6-5771-303d-a785-1b6c5ab0f2d2

Risk Review


Risk meeting March 30th 15:00 PT (Tim Jenness will attend)

Risk items needing review

Jira
serverJIRA
columnskey,summary,type,created,updated,due,assignee,status,days since review
maximumIssues20
jqlQueryproject = "Risk Management" AND issuetype in (RM-Risk, RM-Opportunity) AND status = "Active Risk/Opportunity" AND component = "Data Management" AND "Days Since Review" >= 60 ORDER BY cf[14809] DESC, status DESC, cf[13108] ASC
serverId9da94fb6-5771-303d-a785-1b6c5ab0f2d2

Overdue risks (obligation date passed)

Jira
serverJIRA
jqlQueryproject = "Risk Management" AND issuetype in (RM-Risk, RM-Opportunity) AND status = "Active Risk/Opportunity" AND status = "Active Risk/Opportunity" AND component = "Data Management" AND "Obligation Date" < now() ORDER BY cf[14809] DESC, status DESC, cf[13108] ASC
serverId9da94fb6-5771-303d-a785-1b6c5ab0f2d2

Risk mitigations due at the end of this month

Jira
serverJIRA
columnskey,summary,type,created,updated,due,assignee,reporter,priority,status,resolution
maximumIssues20
jqlQueryproject = "Risk Management" AND issuetype in (RM-Risk, RM-Opportunity) AND status = "Active Risk/Opportunity" AND status = "Active Risk/Opportunity" AND component = "Data Management" AND "Obligation Date" < now() ORDER BY cf[14809] DESC, status DESC, cf[13108] ASC
serverId9da94fb6-5771-303d-a785-1b6c5ab0f2d2

Overdue risk mitigations

 

Jira
serverJIRA
jqlQueryproject = rm AND issuetype = rm-handling AND status = Planned AND component = "Data Management" AND "Anticipated completion date" <= endOfMonth() AND "Anticipated completion date" <= now() ORDER BY status DESC, component ASC, assignee ASC, reporter ASC
serverId9da94fb6-5771-303d-a785-1b6c5ab0f2d2

DMLT Travel & Availability this week


WOM - Workshop on Wednesday

Gregory Dubois-Felsmann on call for jury duty  through  

  • AURA holiday this Friday
Any Other Business


  • Unified builds meeting Wednesday   afternoon, will address preparing builds for the summit.  Limited list of attendees.
  • 2021-04-14 Build Workshop 
    •  Wil O'Mullane will sort out distributing an agenda to others - several people are interested in the content but may not need to attend.  
TCAM Standupas needed
Action review


...