Effective October 1, 2020, Jeff will be reducing his work time to 50%, with 25% on Rubin Observatory and 25% on NOIRLab projects. For Rubin Observatory on Operations contracts and SLAs starting in October.
CAM role for the Long-Haul Networks (WBS 02C.08.03) will go to Cristian Silva as well as his co-chairmanship. We will do an LCR of the LHN WBS from DM to IT.
Updates to be made post-JDR (have we made them yet?):
Risk slides — adding architecture risk, and new requirements on security exposure needs to be increased (could bump this exposure further, due to Huawei regulations; Jeff Kantor will review).
key,summary,type,created,updated,due,assignee,status,days since review
maximumIssues
20
jqlQuery
project = "Risk Management" AND issuetype in (RM-Risk, RM-Opportunity) AND status = "Active Risk/Opportunity" AND component = "Data Management" AND "Days Since Review" >= 60 ORDER BY cf[14809] DESC, status DESC, cf[13108] ASC
serverId
9da94fb6-5771-303d-a785-1b6c5ab0f2d2
Overdue risks (obligation date passed)
Jira
server
JIRA
jqlQuery
project = "Risk Management" AND issuetype in (RM-Risk, RM-Opportunity) AND status = "Active Risk/Opportunity" AND status = "Active Risk/Opportunity" AND component = "Data Management" AND "Obligation Date" < now() ORDER BY cf[14809] DESC, status DESC, cf[13108] ASC
project = "Risk Management" AND issuetype in (RM-Risk, RM-Opportunity) AND status = "Active Risk/Opportunity" AND status = "Active Risk/Opportunity" AND component = "Data Management" AND "Obligation Date" < now() ORDER BY cf[14809] DESC, status DESC, cf[13108] ASC
serverId
9da94fb6-5771-303d-a785-1b6c5ab0f2d2
Overdue risk mitigations
Jira
server
JIRA
jqlQuery
project = rm AND issuetype = rm-handling AND status = Planned AND component = "Data Management" AND "Anticipated completion date" <= endOfMonth() AND "Anticipated completion date" <= now() ORDER BY status DESC, component ASC, assignee ASC, reporter ASC