Project Updates
  • Updated org charts  for Chile - sent to DMLT last week
    • Some iteration on these expected.
  • IT: Jeff Kantor reducing hours.
    • Reflected on org chart above.
  • DOE - data facility - process bring put in place
    • See e-mail to DMLT last week.
    • Managers asked to dampen down wild speculation.
  • SPIE in Japan next year.
    • Abstract submission coming up in November.
    • Victor requests 2-3 people per group/subsystem.
    • DM Frossie/Tim, Gabriele invited to submit a paper
    • T&S minimum footprint - Andy/Tiago? .. all very busy.
    • Also want to avoid cancellations
    • All attendees to be run by Victor/Ranpal; make sure Wil knows before you submit an abstract
  • Issues
    • filter change time .. (longer than spec 120s - no mitigation - Zeljko Ivezic  calculates 1% effect) acceptance review this week
      • very late information - no choice
      • must ship first week oct or camera will be delayed
      • LCR-2007
    • AuxTel - Stubbs and co in Tucson. Resource allocation and timing issues.
      • this managers meeting is place to sort out allocation issues - drive on summit needs attention - spectrogrpah needs software
      • M2 move / AuxTel - Rolando/Mike for both.. Who set priorities .. miscomunicaiton
    • DOME/TMA - moving fast - trying to get Dome for Oct 15 and whatif ..significant for Jeff/Victor Dome and TMA teams ..
      • will have crane, rotating dome, alternative to cladding
      • DOE/NSF directors showing up on Oct 18 ..
Data Facility — DOE investigationWil O'Mullane
  • Nothing to add to last week's e-mail.
  • Letters have been sent to labs; heard nothing back yet.
  • Expecting to put together some sort of evaluation team.
  • Should have this resolved before the end of the year; if possible, carry out evaluation in November.
DMLT F2F meeting
  • The next face-to-face meeting will take place in five weeks.
  • Please make sure your TR is submitted & your accommodation booked at the Creekside Inn (use that link).
  • Please add topic suggestions/requests to the Confluence page.
  •  John Swinbank — provide draft agenda for the October DMLT F2F.  
Risk Review
  • Next meeting of the project Risk Review Board is scheduled for 2019-10-01.
  • All risks which haven't been reviewed in >60 days need to be reviewed.
  • Every risk should have a mitigation action; the post-mitigation risk exposure should be 0–1% due to DM being cost-capped.
    • This is “just book-keeping”
Level 2 Milestones

Test Plans due in the next 45 days

Jira
serverJIRA
columnskey,summary,type,created,updated,due,assignee,reporter,priority,status,resolution
maximumIssues20
jqlQuerylabels = TESTPLAN and resolution = Unresolved and due <= 45d order by id asc
serverId9da94fb6-5771-303d-a785-1b6c5ab0f2d2

Milestones due in the next 45 days

Jira
serverJIRA
columnskey,summary,type,created,updated,due,assignee,reporter,priority,status,resolution
maximumIssues20
jqlQueryproject = DM and labels = L2Milestone and team not in ("Telescope and Site") and resolution = Unresolved and due <= 45d order by id asc
serverId9da94fb6-5771-303d-a785-1b6c5ab0f2d2

  • All Unknown User (mbutler)'s plans being worked on.
  • Outline for LDM-503-11 has been drafted.
    • Should be on agenda for DMLT in October.
  • LDM-503-11b is a Pipelines release; simple test plan expected.
  • LDM-503-10a test plan should go to Wil O'MullaneLeanne Guyfor review.
Any Other Business
DMLT Travel & Availability this week
Review open action itemsWil O'Mullane

...