Project updates
  • Victor initiated use of summit work management and planning Jira Project. Michael R. and Andrew S. did great work getting the system tuned up and ready for use.
  • Next will be travel management for Chile. TR like normal but a Jira ticket to track all updates for Chile travel.
    • Details TBD: watch for announcements.
  • Scope options will need a refresh for JSR.
  • Open Data Framework. April 15th gone without decision... next is some director level meeting. 
    SAC meanwhile went ahead and posted something. 

  • No scheduled project travel in Chile around the Eclipse; no LSST work on the mountain on Eclipse day (July 2).  Kevin R sprint 3 will end a couple of day early to avoid.
  • Steve Ritz had provided two good candidate ITL Type-A devices as a potential swap for AuxTel.
  • In case I did not mention it Giovanni Corvetto has been promoted to LSST Safety Supervisor in Chile (Chuck G is now 50%).
Variances
  • Kevin is beating drums about narratives.
  • Narratives for March due by the coord meeting on Friday morning (26 April).
DM Leadership Team Face-to-Face Meeting, 2019-06-04 to 06
  • Meeting is six weeks away.
  • Please add suggestions for topics to the Confluence page.
  • Put in TRs  and hotel needs to be booked by end April.
Level 2 MilestonesWil O'Mullane

Test Plans due in the next 45 days

Jira
serverJIRA
columnskey,summary,type,created,updated,due,assignee,reporter,priority,status,resolution
maximumIssues20
jqlQuerylabels = TESTPLAN and resolution = Unresolved and due <= 45d order by id asc
serverId9da94fb6-5771-303d-a785-1b6c5ab0f2d2

Milestones due in the next 45 days

Jira
serverJIRA
columnskey,summary,type,created,updated,due,assignee,reporter,priority,status,resolution
maximumIssues20
jqlQueryproject = DM and labels = L2Milestone and team not in ("Telescope and Site") and resolution = Unresolved and due <= 45d order by id asc
serverId9da94fb6-5771-303d-a785-1b6c5ab0f2d2


  •  John Swinbank — automatically sync test plan due dates with PMCS (say, 2 months ahead of milestone due date).  
  •  John Swinbank — drop T&S milestones from Jira query.  
AOBWil O'Mullane


Open todo items
DMLT travel & availability this week
  • John Swinbank at UIUC Monday/Tuesday 22/23 Apr. Will try to be available online; will make it to this meeting.
  • Gregory Dubois-Felsmann on vacation 19-26 April.  Limited availability week of 6-10 May, participating in GMT internal review.

...