  • SIT-Com: Tiago, Patrick - if AUXTel with LATISS these two should be on site in Chile - and Brian (possibly Michael Reuter for EFD)
  • Data Production QA : Lauren , Yusra AlSayyad since it looks like we will be defining procedures as we go, others ..
  • Data Production Facility :  Michelle B, Robert G ,

...


OPS rehearsal II discussion (2020 March 31; 15:00 Pacific; https://bluejeans.com/206063043)

Participants

Agenda

  • decide if we do it with simulations from the base or delay to summit reopening.
    • basically set a schedule
    • if we use LATISS agree ground rules with Patrick (not to interfere with engineering work)
    • comcam?
  • give some clarity on personnel involved and what role they play
  • give some clarity on goals such as
    • which procedures we might develop
    • which requirements  could potentially verify (Jeff Carlin)

Notes

Outstanding questions:

  • Which instrument should we use to drive the rehearsal? Simulations, or AuxTel/LATISS, or ComCam?
  • When do we feel we need to run this rehearsal?
  • Do we need to rethink ops rehearsals given our current situation? E.g. introducing more rehearsals in future, as things start coming back online.
    • Note there is a pre-ops milestone which may fold in to this rehearsal.
    • That milestone implies we want this done by the end of June.