The pre-operations team feel using AuxTel for this rehearsal  rehearsal would provide maximum end to end realism.

(Thouugh Though Corvid-19 may prevent that)

...

  • SIT-Com: Tiago, Patrick - if AUXTel with LATISS these two should be on site in Chile - and Brian (possibly Michael Reuter for EFD)
  • Data Production QA : Lauren , Yusra AlSayyad since it looks like we will be defining procedures as we go, others ..
  • Data Production Facility :  Michelle B, Robert G ,

...


Agenda for OPS rehearsal II discussion (2020 March 31; 15:00 Pacific; https://bluejeans.com/206063043)

Participants


  • decide if we do it with simulations from the base or delay to summit reopening.
    • basically set a schedule
    • if we use LATISS agree ground rules with Patrick (not to interfere with engineering work)
  • give some clarity on personnel involved and what role they play
  • give some clarity on goals such as
    • which procedures we might develop
    • which requirements  could potentially verify (Jeff Carlin)