OpSim Team Weekly Meeting

Oct 30, 2013 - 10:30 PDT/MST


Tucson Location:  LSST Conference Room

Videocom: IP 140.252.24.8 (Direct Dial)

Telecom: 1-866-330-1200 Participant Code 860-9352#

Agenda
  • Top Priority = OpSim Review (ready by Jan end)
  • Deliverables (Review JIRA summary)
    • Understanding and Validating v3.0beta3+ / new Reference Run
    • Document explaining v2.6.1 vs. v3.0; outline?
    • Release of SSTAR v4.0
  • Metrics Framework – timelines/tasks to framework review
  • Daylight Savings Time US starts Sunday


Attendees:  Abi, Steve, Kem, Cathy, Srini, Andy, Zeljko, Victor
Notable
  • OpSim Review is tentatively scheduled for the week of Feb 3, 2014.  It can't slip further out as conflicts with the Gem Show (accommodations will be unavailable) and member travel.  A Dry Run is scheduled for the week of Jan 20.
  • An updated Activity Plan is posted here.  It is a ballpark time estimate and planning document but should reflect the current scope and status of the teams work.
  • v3.0 Simulator:
    • Next steps with the will be to complete tasks needed for the v3.0 release, then start on lookahead and start/stop.
    • Validation runs have been started.
  • v4.0 SSTAR:
    • Close to completion; validation will follow.
    • Will likely be paired with v3.0 as a complete set of tools
  • Framework:
    • Srini will coordinate effort on the design
    • An Internal Design Review will take place in a few weeks (TBD)
  • Deliverables for OpSim Review

Point

Editors

Item/Component

Srini

Cathy

  • Release SSTAR v4.0
  • Document: PostProcessing Code & Use
  • Analysis Framework

Steve

Srini

  • Document: Metrics

Abi

Kem, Steve

  • Document: Path to the Scheduler

Francisco

Kem, Abi

  • V3.0 remaining clean up & release
  • Document: Simulator Requirements
  • Document: Simulator Description & Use

Kem

Abi, Steve

  • Document: Reference Run Package for CCB

 

Cathy

Kem, Francisco

  • Document: Validation
Next week's meeting will shift due to Daylight Savings Time with respect to TUCSON  - so 9:30 PST and 10:30 MST

Action Items
  • All - Add your travel to the Workspace calendar
  • All - Update your JIRA issues to reflect your current status of work
  • Srini – write up the plan for switching bug/tracking software from Mantis to JIRA, with a solution for the Run Log.
  • Cathy - work with Kem and Iain to backup old machines and relocate data to newer machines.
  • Srini's List
    • SSTAR histograms don't get created on opsimblitz1
    • SSTAR doesn't run on Steve's machine
  • No labels