(back to the list of all DMLT meeting minutes)

Discussion Items

ItemWhoNotes
Project Updates
  • Directors review planning
    • no charge nor committee yet
    • 3 days September 7,8,9 (labor day is 6th)
    • Just need to update our slides from rebaseline
    • Apparently they no longer like multiple parallel breakouts so it may be just management and technical in parallel.
    • long discussion on camera and how to present that in the review
    • NSF numbers will not be final. There may be technical probing on potential to actually finish - it all converges on SITCOM
    • Possibly last JSR for EPO - some clarity on what they expect in the review from EPO - what to EPO have to do for an acceptance review.
  • PCW
    • Schedule ok to use P6 . Technically still in flux . Kevin says now Dec 15 (So January is good).
    • We still have not gotten talking points on Satellites from NSF. So we have to say any talk about satellites is under discussion with Agencies refer to Ed (NSF) if Ed is  not there - Steve, Bob, Victor, (wil, leanne, Zeljko if the first 3 not available).
  • Some discussion with tubes on camera, how to we convince ourselves the will not leak over 10 years.
    • Task force chaired by Boyd
    • Kevin looking with endoscope  
    •  need telescope people to understand torque on lines and any potential mods it might need.
  • Camera lift and ComCam lift scheduled Wednsedy
    • staffing issues and travel issues may get in the way any delay would not be technical.
Level 2 Milestones


See also LSST Verification & Validation Documentation and docsteady.lsst.io.

Test Plans due in the next 45 days

Key Summary T Created Updated Due Assignee Reporter P Status Resolution
Loading...
Refresh

Milestones due in the next 45 days

Key Summary T Created Updated Due Assignee Reporter P Status Resolution
Loading...
Refresh

Risk Review




Risk items needing review

Key Summary T Created Updated Due Assignee Status days since review
Loading...
Refresh

Overdue risks (obligation date passed)

T Key Summary Assignee Reporter P Status Resolution Created Updated Due
Loading...
Refresh

Risk mitigations due at the end of this month

Key Summary T Created Updated Due Assignee Reporter P Status Resolution
Loading...
Refresh

Overdue risk mitigations

 

T Key Summary Assignee Reporter P Status Resolution Created Updated Due
Loading...
Refresh

DMLT Travel & Availability this week


WOM on leave next week

RFCs

Overdue

Key Summary Reporter Assignee Created planned end
Loading...
Refresh

Due this week

Key Summary Reporter Assignee Created planned end
Loading...
Refresh

Action Items

Confluence Quick Tasks

DescriptionDue dateAssigneeTask appears on
  • Frossie Economou Will recommend additional Level 3 milestones for implementation beyond just the DAX-9 Butler provenance milestone.   
15 Mar 2022Frossie EconomouDM Leadership Team Virtual Face-to-Face Meeting, 2022-02-15 to 17
  • Kian-Tat Lim Convene a meeting with Colin, Tim, Robert, Yusra to resolve graph generation with per-dataset quantities (likely based on Consolidated DB work).  
18 Mar 2022Kian-Tat LimDM Leadership Team Virtual Face-to-Face Meeting, 2022-02-15 to 17
  • Frossie Economou Write an initial draft in the Dev Guide for what "best effort" support means  
17 Nov 2023Frossie EconomouDM Leadership Team Virtual Face-to-Face Meeting - 2023-Oct-24
  • Convene a group to redo the T-12 month DRP diagram and define scope expectations Yusra AlSayyad 
30 Nov 2023Yusra AlSayyadDM Leadership Team Virtual Face-to-Face Meeting - 2023-Oct-24
11 Dec 2023Gregory Dubois-FelsmannDM Leadership Team Virtual Face-to-Face Meeting - 2023-Oct-24

DMLT-relevant Jira Tickets

Key Summary Reporter Assignee Created Due
Loading...
Refresh