Date | Activity | Description and Details |
---|
April 2018 | Archiver machine shipped from NSCA to Tucson (April 1st). | - For installation into AuxTel test stand.
|
May 2018 | "Simple" implementation of Gen3 middleware. | - i.e. gen3 butler + superTask
|
| Spectrograph Test Stand Operations (Rehearsal is LDM-503-04b, which is currently in PMCS as June 1st). | - Need NFS export of files in Tucson.
- Need ability to pull files off DAQ and decide which get forwarded to NCSA for archiving.
- Nice to have a "developer-level" instance of the Science Platform for accessing raw data (notebook only).
- Note: have ability to generate spectra with a lamp at this point.
Is there butler access in NCSA?
|
August 2018 | Some version of spectrophotometric algorithm wrapped in script form. | - Hope is that this is implemented in Gen3 middleware, but will use at this point.
|
November 2018 | Spectrograph assembled in AuxTel Dome (Nov 30th). | - Per Patrick: this date could slip a little based on hardware and site readiness.
- Need ability to pull files off DAQ and forward to NCSA for archiving. Desire flexibility to decide which files get forwarded. A lot of these data will be junk at first.
RHL Same questions as for "Spectrograph Test Stand Operations" - : ITC (possibly what is in Tucson test stand), ITC staff (maybe) for installation, and Jim Parsons for onsite integration and support.
|
Base Data Center available (tentative) | - Need to move IT security systems out of the NOAO Base Facility to new Data Center. This will be done as a "flag day" coordinated with Chilean ITC group.
|
January 2019 | DRP spectrophotometric pipeline payload ready in Gen3 middleware framework (late January). | - LDF begins integration into production system.
|
Spectrograph First Light on AuxTel (Jan 28th). | - "Begin to get real data."
|
June 2019 | Routine Data Collection with Spectrograph (June 30th). | - Begin production processing of spectrophotometric pipeline.
|
EFD at Base | - Need to confirm with Chuck that LDF can delay commissioning cluster deployment until this time.
- Will need to move the Summit AuxTel archiving system to the new Base Center. Coordinate downtime with AuxTel operations.
|