See the discussion of epics to roll over to S15 at Data Release Production S15 Planning. Given that, focus on finishing the measurement framework overhaul this cycle.

This table summarises the outstanding story point allocations assuming all work scheduled for the current sprint (Science Pipelines DM-W15-4) is completed on schedule.

EpicAssigneeSPs
DM-1074Swinbank9 (estimated)
DM-1099Swinbank10
 Bosch13
 Gee4
DM-1100Gee3 + unplanned (DM-280)
 Bosch4
 Lupton2
DM-1101Gee18
 Bosch6

(Framework overhaul in green)

Totals per assignee:

AssigneeSP total
Bosch23
Gee25 + unplanned
Lupton2
Swinbank19

W15 should close at end February (it is a 5 month cycle: October through Feb). Following the AHM, that leaves two weeks of work, or 1/12 of a cycle. Plausible SP totals are:

AssigneeCalculationSP total
Bosch87 / 12; assuming full time on LSST7
Gee157 / (2 * 12)6
Lupton0.5 * 6 SPs/month3
Swinbank87 / 127

Based on these numbers, it is not plausible to suggest that all work scheduled for these epics in W15 will be completed.

 

  • No labels