See the discussion of epics to roll over to S15 at Data Release Production S15 Planning. Given that, focus on finishing the measurement framework overhaul this cycle.
This table summarises the outstanding story point allocations assuming all work scheduled for the current sprint (Science Pipelines DM-W15-4) is completed on schedule.
Epic | Assignee | SPs |
---|---|---|
DM-1074 | Swinbank | 9 (estimated) |
DM-1099 | Swinbank | 10 |
Bosch | 13 | |
Gee | 4 | |
DM-1100 | Gee | 3 + unplanned (DM-280) |
Bosch | 4 | |
Lupton | 2 | |
DM-1101 | Gee | 18 |
Bosch | 6 |
(Framework overhaul in green)
Totals per assignee:
Assignee | SP total |
---|---|
Bosch | 23 |
Gee | 25 + unplanned |
Lupton | 2 |
Swinbank | 19 |
W15 should close at end February (it is a 5 month cycle: October through Feb). Following the AHM, that leaves two weeks of work, or 1/12 of a cycle. Plausible SP totals are:
Assignee | Calculation | SP total |
---|---|---|
Bosch | 87 / 12; assuming full time on LSST | 7 |
Gee | 157 / (2 * 12) | 6 |
Lupton | 0.5 * 6 SPs/month | 3 |
Swinbank | 87 / 12 | 7 |
Based on these numbers, it is not plausible to suggest that all work scheduled for these epics in W15 will be completed.