DMLT Meeting Goals

  • Weekly meeting to keep the DM leadership team coordinated, informed, and in agreement on the vision, priorities, and challenges facing DM construction, including surfacing and resolving issues and ambiguities needing our attention. The goal of this meeting is to provide information and decisions that help each one of us better direct our own (or our team's) activities.

Discussion Items

Guidelines: Propose items in line with the meeting rationale (see above); include as much information in the agenda notes; summarize, don't go into details while on the call; maximize time available for discussion. 

ItemWho

Notes

Status of LDM-503-n milestones
  • LDM-503-1 (WISE data in PDAC)
    • Update from Gregory Dubois-Felsmann.
    • RFC for Science Platform Design Document & LDM-503-1 test spec today.
    • “Will flush out the test report after that”.
  • LDM-503-4 & LDM-503-4b
Travel requestsWil O'Mullane
  • Travel requests must be submitted 21 days before travel starts.
    • Except in special circumstances.
    • Certain individuals got special mention.
Planning package statusWil O'Mullane
  • Victor has asked for a planning "status" and revised ETC by 27 March.
    • This should be a brief status for him which may lead to some discussion. EAC 2018  should have templates.
    • Not to (re)cost everything just sense if we are on budget.
    • Which activities might be impacted by key risks?
    • 28th & 29th March potential meetings with Victor — John available? (thumbs up)
    • Please time box this activity.
  • Also risk refresh due by 15 April form the T/CAMs.
Scope Options (by April 30)

https://www.dropbox.com/sh/ggh36s4gc16xvn8/AAAL1e6NTgliNIQFS58H8piUa?dl=0

Just checking on the update from last year ..

  • Please only update the file for your subsystem but have a look at the System level scope options and comment as necessary.
  • Add new Scope and De-scope options to the bottom of the existing lists in the appropriate tab.
  • You need to edit existing Available entries. Please don't delete any rows. Update the status (see #5 below), refresh dates in the future (see#7 below) if option is still available, and update the language to be consistent with Project status. No action is required if the entry is in state Implemented or Unavailable.
  • Each subsystem should aim for De-scope options to be around 10% of your remaining budget in current day dollar amounts.
  • The status of the entries can only be Available, Unavailable or Implemented
  • When you change an entry please add an explanatory note in the comment field.
  • Early date and Latest date columns need to be to quarterly fidelity 1/01, 04/01, 07/01, 10/01 and year rather than just year.
  • Some comments in red preceded with "ZI" are comments for your reference/consideration from Zeljko.
  • Subsystem scientists should write/review the scientific impacts. Zeljjo and Victor will do a final review of all impacts.
  • SE & Commissioning: a new blank sheet has been created for Commissioning, any commissioning related (de)scope options should be moved from the SE sheets into this new commissioning one and apportion the cost/value for NSF vs DOE.
May DMLT F2FWil O'Mullane
RenameWil O'Mullane
  • Is happening.
    • The telescope and the survey will both get renamed.
    • Probably in 2019 (or maybe 2020).
Overdue RFCs
Change Control Board report
  • Change requests of interest to DM
  • LSE-75 is being voted upon (TCS-DM interface).
  • LSE-72 (OCS-DM interface) is being worked on.
  • LCR-983: CCOB/DM testing. Still unclear as to whether camera and DM can coordinate on this.
  • Base requirements: still waiting on cost impacts from Jeff Barr.
SnowPACGregory Dubois-Felsmann

Decadal survey inputs .. Many talks mentioned LSST

billion object spectra survey - will all be on the web

Wide discussion on software and software careers, have lessons been learned on funding development. LSST did this well. Smaller projects are still under funded for software. Open source also discussed.

Whitepapers will be written over next 6 - 12 months. Large spectra survey, Software fellowships .. citable software. Propose NSF to have software calls. How to get software in to gradschool without squeezing out astrophysics..


DMLT travel & availability this week

Overdue RFCs

Key Summary T Created Updated Due Assignee Reporter P Status Resolution
Loading...
Refresh

Past action items

Open DMLT actions

DescriptionDue dateAssigneeTask appears on
  • Frossie Economou Will recommend additional Level 3 milestones for implementation beyond just the DAX-9 Butler provenance milestone.   
15 Mar 2022Frossie EconomouDM Leadership Team Virtual Face-to-Face Meeting, 2022-02-15 to 17
  • Kian-Tat Lim Convene a meeting with Colin, Tim, Robert, Yusra to resolve graph generation with per-dataset quantities (likely based on Consolidated DB work).  
18 Mar 2022Kian-Tat LimDM Leadership Team Virtual Face-to-Face Meeting, 2022-02-15 to 17
  • Frossie Economou Write an initial draft in the Dev Guide for what "best effort" support means  
17 Nov 2023Frossie EconomouDM Leadership Team Virtual Face-to-Face Meeting - 2023-Oct-24
  • Convene a group to redo the T-12 month DRP diagram and define scope expectations Yusra AlSayyad 
30 Nov 2023Yusra AlSayyadDM Leadership Team Virtual Face-to-Face Meeting - 2023-Oct-24
11 Dec 2023Gregory Dubois-FelsmannDM Leadership Team Virtual Face-to-Face Meeting - 2023-Oct-24
02 May 2024Frossie EconomouDMLT Meeting - 2024-04-22
22 May 2024 DMLT Meeting - 2024-04-22
22 May 2024Fabio HernandezDMLT Meeting - 2024-04-22
  • Richard Dubois USDF part in data facilities for PSTN-017 and distrib processing ? 
22 May 2024Richard DuboisDMLT Meeting - 2024-04-22
  • Tim Jenness - section on middleware for PSTN-017  
22 May 2024Tim JennessDMLT Meeting - 2024-04-22
  • Cristián Silva - section on summit/data acquisition  for PSTN-017  
22 May 2024Cristián SilvaDMLT Meeting - 2024-04-22