(back to the list of all DMLT meeting minutes)
Date
Attendees
- Unknown User (ciardi)
- Unknown User (xiuqin)
- Unknown User (rlambert)
- Margaret Gelman
- Donald Petravick
- Frossie Economou (vacation)
- Gregory Dubois-Felsmann
- Kian-Tat Lim
- John Swinbank
- Jacek Becla
- Simon Krughoff
- Jim Bosch
- Mario Juric
- Jeff Kantor
- Ashley Sands (observer)
Goals
- Weekly coordination meeting to discuss and resolve management items, project communications, external contacts, etc.
Discussion items
Item | Who | Notes |
---|---|---|
DM Leadership Team Meetings in May, November | Jeff Kantor | May 18 - 20 F2F at NCSA, fly Sunday, Monday morning will be on agenda but will try to keep light Changing November F2F at Princeton to 11/16 - 20 (DESC meeting and ADASS week before, possible Camera conflicts) |
Other conferences/meetings | Jeff Kantor | IVOA Interop Italy in June John Swinbank will attend, schedule overall VO side session at May DM LT SciPy Austin July 6 - 11 - Tim Jenness, Yusra AlSayyad, IPAC TBD |
T/CAM training sessions | Jeff Kantor | March 25 - 26 went well, including proposal and example in work for LDM-240, PMCS, JIRA Agile integration April 8 - 9, attendance is set, Laurie Thomas for travel information, parking permits, for temp offices Glenaver |
WBS changes | Jeff Kantor | Will notify T/CAMs when LCR-343 WBS changes have been implemented in PMCS New policy is RFC/TCT process for changes to WBS L3 and below (not LSST CCB) T/CAMs can do RFC to move effort between Level 3 WBS elements as long as it does not affect Level 2 bottom line cost, schedule Kevin Long will be a watcher on all PMCS, WBS RFCs |
LDM-240 updates | Jeff Kantor | As of last DMLT: Kian-Tat Lim working on first few rows of sheet, submitted to Gregory Dubois-Felsmann for integration and review Overall schedule: All FY16+ column changes (with first-level estimate of resources required) to GPDF due 20150331 DMLT review and agree on changes due 20150407 Add additional descriptive material, detailed estimates of resources required*, and linkages to DPDD due 20150422 DMLT Review and agree on changes due 20150430 *Next iteration: Add linkages to JIRA Agile epics |
Descopes and upscopes | Jeff Kantor | Received input from KTL on Upscope DM-01, DM-02 |
AMCL Presentation | Jeff Kantor | AMCL slides in from all except NCSA |
Risk Management | Jeff Kantor | Jeff Kantor Will do top 10 for risk review and trigger DM-043 in JIRA and Risk Register (look at 18-bit example) Kian-Tat Lim DM-065 increasing in probability, will update register |
Action items
REMINDER: T/CAMs Turn in Monthly Progress Report inputs, variance reports in eCAM tool by 15th of following month
- Margaret Gelman, Jacek Becla, John Swinbank, Simon Krughoff, Xiuqin Wu, Frossie Economou WBS field changes needed in JIRA Agile
- Jacek Becla send master version of changes to 02C.06 to Gregory Dubois-Felsmann
- Jacek Becla Check estimate of upscope DM-01
- Kian-Tat Lim Do revised wording of upscope DM-02
- Kian-Tat Lim Send upscope Sizing Model sheets to Jeff Kantor
- Jeff Kantor Talk with Daniel Calabrese regarding "large person" letter format
- Gregory Dubois-Felsmann, Robert Lupton Confirm no actions in Calibration plan needed for CD3
- Donald Petravick get point of contact for DMLT F2F May 18 - 20 at NCSA to Jeff Kantor
2 Comments
Unknown User (xiuqin)
Jeff Kantor "All FY16+ column changes (with first-level estimate of resources required) to GPDF due 20150331." The estimate of resources required is not part of the LDM-240. Do you need extra information on this?
Jeff Kantor
Effort estimation is not strictly a part of LDM-240, but you should make changes to the columns with some idea of what you may be doing to the resources required to implement the plan. If, for example, you move a large segment of work earlier or later, you should probably point this out.
In any case, we will do a more formal evaluation of that AFTER the initial proposed column changes, which should not be considered final until the effort impact is analyzed. This will be done by examining the milestones and creating "meta-epics" which the T/CAMs will estimate.