Date/Time

(Default schedule is second Thursday of Month.)

0800 PT/0900 MT/1000 CT/1100 ET/1300 CLT

Meeting Online Connections:

Join Zoom Meeting
https://fiu.zoom.us/j/602918755?pwd=dmpheWkzZ0I2YWF3OGpWNzlUL3ltUT09

Meeting ID: 602 918 755
Passcode: 000000
One tap mobile
+16468769923,,602918755# US (New York)
+13017158592,,602918755# US (Germantown)

Dial by your location
        +1 646 876 9923 US (New York)
        +1 301 715 8592 US (Germantown)
        +1 312 626 6799 US (Chicago)
        +1 669 900 6833 US (San Jose)
        +1 253 215 8782 US (Tacoma)
        +1 346 248 7799 US (Houston)
Meeting ID: 602 918 755
Find your local number: https://fiu.zoom.us/u/aedBVv78VU

Join by SIP
602918755@zoomcrc.com

Join by H.323
162.255.37.11 (US West)
162.255.36.11 (US East)
115.114.131.7 (India Mumbai)
115.114.115.7 (India Hyderabad)
213.19.144.110 (Amsterdam Netherlands)
213.244.140.110 (Germany)
103.122.166.55 (Australia)
209.9.211.110 (Hong Kong SAR)
64.211.144.160 (Brazil)
69.174.57.160 (Canada)
207.226.132.110 (Japan)
Meeting ID: 602 918 755
Passcode: 000000

Meeting Recording:

TBD

Attendees

  • Gisella Kapus (GK) ESnet

Goals

  • Coordination of networking activities across Rubin Observatory

Discussion items

Time

(PT)

Item

Who

Notes


NET Action Items Status

Reminder: Work on your action items: International Communications (aka Long-Haul Networks)

Network activities schedule (subject to COVID19 impacts):

January - Continued work on  Rubin Observatory Network Verification Plan (including JIRA). 

February - Completed draft  Rubin Observatory Network Verification Plan (including JIRA).

March - Scheduled Rubin Observatory Networks Pre-Verification Review for May 18 - 19

April - Prepare for Rubin Observatory Networks Pre-Verification Review.  Submit LSST Change Request to update LSE-78 Rubin Observatory Network Design (including Chilean, International, and US networks), and related milestones in PMCS.   Complete LDM-732 Rubin Observatory Networks Pre-verification Baseline.

May - Complete FY19, FY20 NET Reports and Technical Document

June - Conduct and respond to actions from Rubin Observatory Networks Pre-Verification Review.  Meet with GlobalNOC re VNOC support.

July  - Pre-Ops Rehearsal 2 testing.

August - Ops Rehearsal 2/Pre-verification testing.

September - Cisco ACI review, Huawei analysis 

October - Start Verification Testing, LS restart, LS - SCL 40G upgrade. (hopefully) - 

November - Update Rubin Observatory Operations & Management Plan, USDF Selection, CP Restart, Network Contracts and SLAs.

December - Updates on G-NOC service progress, Brazil path (Huawei) options, planning for US Data Facility at SLAC

January - Updates on G-NOC service progress, Brazil path (Huawei) options, planning for US Data Facility at SLAC

February - Agreed to propose NSF to DOE include funding of VNOC and Huawei in the ops proposal / USDF continuing discussing footprints, power cooling. 

March - Keep 2x20GB through Chicago during Construction. End of Construction Aug-FY23, would need 2x100 to SLAC.

New processing facility in UK, some data that goes to Europe will go to UK (1/4), likely 75% of data will be processed in Europe so more data will come back, so the 2x10GB link will likely increase 7-7.5GB per year


Update on CONUS Networks

CONUS Networks, including ESnet:

Paul: No updates

Jeronimo: No changes. We started to work on  boca - atlanta


Chilean/International Networks Update

Developments in La Serena and end-to-end service to NCSA for upcoming Auxiliary Telescope Traffic and general (internet, mail, voice) traffic

Cristian: Auxtel run next week. 

Albert: No updates. La Serena - Santiago incident was never closed by the provider. 



USDF & NCSA - CC-IN2P3 Networks update

Unknown User (kollross)

Mark Foster

Richard Hughes-Jones

Stuart McLellan

USDF & NCSA - CC- IN2P3 network:

Mark : Meetings with Phil talking about operations support. Richard Dubois will get involved to get processes created. New building working on. Router renovations in support for the USDF. Handoff between EsNet and SLAC being worked for Jeronimo and Paul. Perfsonar nodes discussions, where t place them.

Matt:

Richard:


Other Discussion Topics

By topic


Rubin Observatory Network Verification:

We will be talking about this during the NET meeting. 

Rubin Observatory Networks, SLAs for Operations:

Julio: Nothing new FIU

Albert: Pending conversation

Virtual NOC: 

After 

Document update status summary

LSE-78: 

LSE-479: 

O&M: Some structure for the NET meeting.


Other businessAny

NET Meeting: Review by Julio


Wrap up and next meeting

Wrap up and Next meetings:  

 

All meetings at 0800 PT/0900 MT/1000 CT/1100 ET/1300 CLT (subject to time changes)

Action items 

  •  
  •